Skip to main content

AI assistant

Sign in to chat with this filing

The assistant answers questions, extracts KPIs, and summarises risk factors directly from the filing text.

SANDFIRE RESOURCES LIMITED Interim / Quarterly Report 2013

Apr 16, 2013

65773_rns_2013-04-16_fd6710a3-5591-4ecf-8e0f-96246859e760.pdf

Interim / Quarterly Report

Open in viewer

Opens in your device viewer

March 2013 Quarterly Report

Webcast – Karl Simich, Managing Director and CEO 17 April 2013

Access this presentation at: http://www.brrmedia.com/event/111178 http://www.sandfire.com.au

Page: 1 Page: 1

Forward-Looking Statements

  • This presentation has been prepared by Sandfire Resources NL. This document contains background information about Sandfire Resources NL current at the date of this presentation. The presentation is in summary form and does not purport be all inclusive or complete. Recipients should conduct their own investigations and perform their own analysis in order to satisfy themselves as to the accuracy and completeness of the information, statements and opinions contained in this presentation.

  • This presentation is for information purposes only. Neither this presentation nor the information contained in it constitutes an offer, invitation, solicitation or recommendation in relation to the purchase or sale of shares in any jurisdiction.

  • This presentation may not be distributed in any jurisdiction except in accordance with the legal requirements applicable in such jurisdiction. Recipients should inform themselves of the restrictions that apply in their own jurisdiction. A failure to do so may result in a violation of securities laws in such jurisdiction.

  • This presentation does not constitute investment advice and has been prepared without taking into account the recipient's investment objectives, financial circumstances or particular needs and the opinions and recommendations in this presentation are not intended to represent recommendations of particular investments to particular persons. Recipients should seek professional advice when deciding if an investment is appropriate. All securities transactions involve risks, which include (among others) the risk of adverse or unanticipated market, financial or political developments.

  • To the fullest extent permitted by law, Sandfire Resources NL, its officers, employees, agents and advisers do not make any representation or warranty, express or implied, as to the currency, accuracy, reliability or completeness of any information, statements, opinions, estimates, forecasts or other representations contained in this presentation. No responsibility for any errors or omissions from this presentation arising out of negligence or otherwise is accepted.

  • This presentation may include forward-looking statements. Forward-looking statements are only predictions and are subject to risks, uncertainties and assumptions which are outside the control of Sandfire Resources NL. Actual values, results or events may be materially different to those expressed or implied in this presentation. Given these uncertainties, recipients are cautioned not to place reliance on forward looking statements. Any forward looking statements in this presentation speak only at the date of issue of this presentation. Subject to any continuing obligations under applicable law and the ASX Listing Rules, Sandfire Resources NL does not undertake any obligation to update or revise any information or any of the forward looking statements in this presentation or any changes in events, conditions or circumstances on which any such forward looking statement is based..

Competent Person’s Statement

  • The information in this public presentation that relates to Exploration Results and Mineral Resources is based on information compiled by Mr John Evans who is a Fellow of the Australasian Institute of Mining and Metallurgy. Mr Evans is a permanent employee and Director of Sandfire Resources NL. Mr Evans has sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as a Competent Person as defined in the 2004 Edition of the Australasian Code of Reporting of Exploration Results, Mineral Resources and Ore Reserves. Mr Evans consents to the inclusion in the report of the matters based on his information in the form and context in which it appears.

==> picture [216 x 473] intentionally omitted <==

Page: 2

==> picture [10 x 10] intentionally omitted <==

==> picture [10 x 11] intentionally omitted <==

==> picture [10 x 10] intentionally omitted <==

==> picture [10 x 11] intentionally omitted <==

==> picture [10 x 10] intentionally omitted <==

==> picture [10 x 10] intentionally omitted <==

==> picture [10 x 11] intentionally omitted <==

Highlights

Safety Mining Processing Production & Sales Exploration Summary

==> picture [591 x 473] intentionally omitted <==

Page: 3

Production and Operations

Continued improved safety performance

==> picture [7 x 7] intentionally omitted <==

Open pit completed in April 2013, transitioning to wholly underground operations Ramp-up of underground mine on schedule Plant ramp-up and optimisation continuing On track for nameplate production rates from mid-CY 2013

==> picture [7 x 7] intentionally omitted <==

==> picture [7 x 7] intentionally omitted <==

==> picture [7 x 8] intentionally omitted <==

==> picture [7 x 8] intentionally omitted <==

Contained metal production Sep 2012 Qtr Dec 2012 Qtr Mar 2013 Qtr Year to Date
COPPER
Concentrator - 7,962 11,632 19,594
DSO 20,175 8,430 2,051 30,656
Total Copper (tonnes) 20,175 16,392 13,683 50,250
GOLD
Concentrator - 3,938 6,287 10,225
DSO 6,161 6,241 3,167 15,569
Oxide gold 1,174 4,516 2,609 8,299
Total Gold (ounces) 7,335 14,695 12,063 34,093

==> picture [216 x 473] intentionally omitted <==

Page: 4

Exploration

In-mine mapping has revealed numerous insights into structural controls, extending exploration opportunities near-mine, including the DeGrussa offset target

==> picture [8 x 8] intentionally omitted <==

Progressing Ore Reserve and Mineral Resource upgrade including extensions to Conductor 4 and Conductor 5 from drilling including:

==> picture [8 x 8] intentionally omitted <==

Conductor 4 – 10.6m @ 4.46% Cu testing the interpreted eastern extension

==> picture [7 x 8] intentionally omitted <==

Conductor 5 – 26.1m @ 7.2% Cu and 3.1g/t Au (existing model estimated 11m), 28.3m @ 5.3% Cu and 2.7g/t Au (existing model estimated 8m), 15.2m @ 8.6% Cu and 2.3g/t Au (existing model estimated 7m)

==> picture [7 x 7] intentionally omitted <==

Exciting new near-mine exploration results and regional targets

==> picture [8 x 8] intentionally omitted <==

Financial and Corporate

First $50M debt repayment completed to reduce debt to $330M, with further funds deposited for the next scheduled payment of $45M in June 2013

==> picture [8 x 9] intentionally omitted <==

==> picture [216 x 473] intentionally omitted <==

Page: 5

LTIFR of 2.6 at March Quarter-end, reduced from December Quarter-end

==> picture [8 x 7] intentionally omitted <==

1 lost time injury sustained for the Quarter Safety performance in line with targets established in Safety Management Action Plan

==> picture [8 x 7] intentionally omitted <==

==> picture [8 x 7] intentionally omitted <==

==> picture [353 x 140] intentionally omitted <==

==> picture [529 x 337] intentionally omitted <==

==> picture [519 x 78] intentionally omitted <==

Page: 6

OPEN PIT

Stage 1 open pit completed December 2012 – 7.7Mbcm mined

==> picture [6 x 7] intentionally omitted <==

Stage 2 open pit completed mid-April 2013 – 5.4Mbcm mined, extracting remaining sulphide and copper and gold oxide material

==> picture [6 x 7] intentionally omitted <==

UNDERGROUND

Three stopes developed and in production – 487,718 tonnes of sulphide ore mined to date

==> picture [6 x 7] intentionally omitted <==

Current underground mining rate of 1.2Mtpa – on target to achieve 1.5Mtpa steady-state from mid-CY2013

==> picture [6 x 7] intentionally omitted <==

Paste plant commissioning underway – first stope paste poured in early April 2013

==> picture [6 x 7] intentionally omitted <==

Evans Decline now +2km from the portal , 340m below surface Total underground development progressed to 12.8km

==> picture [6 x 7] intentionally omitted <==

==> picture [6 x 7] intentionally omitted <==

==> picture [508 x 130] intentionally omitted <==

==> picture [508 x 309] intentionally omitted <==

Page: 7

MILL THROUGHPUT

310,727 tonnes milled – 24% increase vs. December Quarter

==> picture [6 x 7] intentionally omitted <==

Steady increase in tonnes processed: on track to achieve nameplate target of 375,000t per quarter from mid-CY 2013

==> picture [6 x 7] intentionally omitted <==

RECOVERY

Achieved recoveries of 85-90% for primary underground ore when processed through the Concentrator – targeting nameplate +90%

==> picture [6 x 7] intentionally omitted <==

Recovery increased from 65% (Dec Quarter) to 80% (March Quarter)

==> picture [6 x 7] intentionally omitted <==

==> picture [523 x 198] intentionally omitted <==

----- Start of picture text -----

Nameplate target
24%
251,016t 310,727t
----- End of picture text -----

==> picture [523 x 200] intentionally omitted <==

----- Start of picture text -----

Nameplate target
65% 80%
----- End of picture text -----

Page: 8

MILL THROUGHPUT

310,727 tonnes milled – 24% increase vs. December Quarter

==> picture [6 x 7] intentionally omitted <==

Steady increase in tonnes processed: on track to achieve nameplate target of 375,000t per quarter from mid-CY 2013

==> picture [6 x 7] intentionally omitted <==

RECOVERY

Achieved recoveries of 85-90% for primary underground ore when processed through the Concentrator – targeting nameplate +90%

==> picture [6 x 7] intentionally omitted <==

Recovery increased from 65% (Dec Quarter) to 80% (March Quarter)

==> picture [6 x 7] intentionally omitted <==

CONCENTRATE & METAL PRODUCTION

48,085 tonnes of concentrate produced – 31% increase vs. December Quarter (target: 75,000 tonnes mid-CY 2013)

==> picture [6 x 7] intentionally omitted <==

11,632 tonnes of contained copper produced – 46% increase vs. December Quarter (target: 19,200 tonnes from mid CY-2013)

==> picture [6 x 7] intentionally omitted <==

==> picture [523 x 198] intentionally omitted <==

----- Start of picture text -----

Nameplate target
31%
36,578t 48,086t
----- End of picture text -----

==> picture [523 x 200] intentionally omitted <==

----- Start of picture text -----

Nameplate target
46%
7,962t 11,632t
----- End of picture text -----

Page: 9

==> picture [7 x 8] intentionally omitted <==

==> picture [7 x 7] intentionally omitted <==

==> picture [7 x 7] intentionally omitted <==

Increasing monthly recoveries, targeting +90% by mid-CY 2013 – constrained to mid-CY2013 by:

Lower recoveries (+60%) for transitional open pit sulphide material, as previously announced Head grade from initial stopes in Conductor 1 of ~4% Cu: progressing into higher grade DeGrussa stopes ( first 15 days of April 2013: ~3,000t Cu production at 5.6% Cu feed grade; +85% recovery )

==> picture [7 x 7] intentionally omitted <==

==> picture [7 x 8] intentionally omitted <==

Achieved concentrate specification

Successful 2-day plant shut-down completed late February 2013:

Tailings thickener capacity increased stability

==> picture [7 x 8] intentionally omitted <==

SAG mill grate modifications to improve ore retention Cleaner circuit hopper mods to improve plant stability Shut-down and shorter month constrained copper production

==> picture [7 x 8] intentionally omitted <==

==> picture [7 x 8] intentionally omitted <==

==> picture [7 x 8] intentionally omitted <==

Optimisation continuing over the June Quarter in line with ramp-up schedule

==> picture [7 x 7] intentionally omitted <==

==> picture [539 x 225] intentionally omitted <==

==> picture [539 x 222] intentionally omitted <==

Page: 10

  • Variation in head feed grade between stopes (generally 4-6% Cu)

  • Targeted recovery range (88-93%) varies with feed grade due to fixed tail grade

  • Results in effective monthly production targets ranging from 4,500-7,000 tonnes per month

  • As underground development and stoping progresses further, blending for plant feed will minimise variation – underpinning the target quarterly copper production of 19,250t Cu (6,400t Cu per month)

==> picture [542 x 330] intentionally omitted <==

----- Start of picture text -----

Target first 3 years
Target based on quarterly feed
Head feed Head feed
4.9% 4.7%
----- End of picture text -----

==> picture [524 x 86] intentionally omitted <==

Page: 11

==> picture [9 x 9] intentionally omitted <==

==> picture [9 x 9] intentionally omitted <==

==> picture [9 x 9] intentionally omitted <==

Concentrator production has steadily ramped up following the start of commissioning in October 2012 During the ramp-up of underground mine production, transitional open pit sulphide material is being processed along with underground ore This will continue during the June Quarter, with production forecast to be sourced wholly from underground from the September 2013 Quarter onwards

==> picture [533 x 284] intentionally omitted <==

==> picture [523 x 124] intentionally omitted <==

Page: 12

• Increased Quarterly copper sales of 12,297t Cu and 10,155oz Au

  • Last high-grade DSO shipment completed in early January 2013

  • Low grade ~30,000t at +10% Cu to complete the DSO sales program

  • Concentrate shipments progressing as scheduled

==> picture [539 x 264] intentionally omitted <==

==> picture [540 x 143] intentionally omitted <==

Page: 13

Metal production Q1-Q3FY13 – Actual Q1-Q3FY13 – Actual Q4FY13 – Guidance To June 2013 – Guidance To June 2013 – Guidance
Cu(kt) Au(koz) Cu(kt) Au(koz) Cu(kt) Au(koz)
Concentrator 20 10 15 7 35 17
DSO 30 16 - - 30 16
Oxide gold - 8 - 3 - 11
Total – 2012/2013 50 34 15 10 65 44
DSO 4 2 4 2
Oxide gold - 1 - 1
Total – 2011/2012 4 3 4 3
Total – Project to date 54 37 15 10 69 47
  • Full year concentrator production guidance maintained at 35kt Cu and 17koz Au

  • Final sales results for prior quarter DSO sales has marginally reduced total DSO production year to date (DSO production completed during the March Quarter)

Page: 14

+30km strike length prospective for VMS mineralisation

==> picture [34 x 16] intentionally omitted <==

----- Start of picture text -----

150m
----- End of picture text -----

  • VMS mineralising environment confirmed over +30km long, 2km wide corridor

  • Minimal exploration below 100m : host sequence at depth still to be explored

  • DeGrussa deposit extents have a strike length of just 1.2km : small footprint, high value

Page: 15

Area available for mapping

  • In-mine mapping over small area opened up to date has revealed numerous insights into structural controls

  • New targets delivered from these initial theories and extrapolation from within the near-mine area

150m

Page: 16

  • Multiple target zones identified

  • Extending exploration opportunity nearmine

  • Structural geology delivering robust targets

Page: 17

==> picture [684 x 442] intentionally omitted <==

One drillhole completed to test the interpreted eastern extension of the C4 orebody – intersected 10.6m @ 4.46% Cu.

  • Resources will be updated for C4 to reflect this intersection and the increased knowledge of bounding structures and orebody morphology

Page: 18

==> picture [649 x 446] intentionally omitted <==

Thickest intersection of C5 massive sulphide drilled to date

  • Potential for resource increase (Main and Upper Zones) towards Merlot Fault

  • 1 conventional and 3 directional drillholes completed during Q1 2013

  • C5 resource being remodelled to reflect thicker central zone

Page: 19

==> picture [9 x 9] intentionally omitted <==

==> picture [9 x 9] intentionally omitted <==

==> picture [9 x 9] intentionally omitted <==

==> picture [9 x 10] intentionally omitted <==

==> picture [9 x 9] intentionally omitted <==

==> picture [9 x 9] intentionally omitted <==

==> picture [9 x 9] intentionally omitted <==

Concentrator commissioning and underground mine ramp-up continuing as planned Optimisation of grade, recoveries and throughput advancing On track for nameplate production rates from mid-CY2013 Successful transition from open pit to underground mining operations Ore Reserve and Mineral Resource upgrade in progress First scheduled $50M debt repayment completed $45M deposited for the end June 2013 scheduled repayment

Australia’s newest copper producer.

==> picture [345 x 473] intentionally omitted <==

Page: 20

March 2013 Quarterly Report

Webcast – Karl Simich, Managing Director and CEO 17 April 2013

Access this presentation at: http://www.brrmedia.com/event/111178 http://www.sandfire.com.au

Page: 21 Page: 21

March 2013 Quarter
Tonnes
Grade (% Cu)
Grade (g/t Au)
Contained Copper
(t)
Contained Gold
(oz)
DSO
Mined
-
-
-
-
-
Crushed
19,925
10.3
4.9
2,051
3,167
DSO sales
17,649
16.9
3.7
2,989
2,072
Concentrator
Mined
447,425
5.2
1.6
23,442
23,488
Milled
310,727
4.7
1.7
14,540
17,442
Concentrate produced
48,085
24.2
4.1
11,632
6,287
Concentrate sold
38,418
24.2
4.4 9,308
5,434
Oxide gold
Mined
-
-
-
-
-
Milled (toll treatment)
25,251
-
3.5
-
2,882
Gold production
-
-
-
-
2,609
Gold sales
-
-
-
-
2,609
Total
Mined
447,425
5.2
1.6
23,442
23,488
Crushed/Milled
355,903
4.7
2.1
16,591
23,491
Copper production
68,010
20.1
4.3
13,683
9,454
Gold production
-
-
-
-
2,609
Contained metal
-
-
-
13,683
12,063
Copper and gold sales
56,067
21.9
-
12,297
10,115

Page: 22

FY2013 Year to Date
Tonnes
Grade (% Cu)
Grade (g/t Au)
Contained Copper
(t)
Contained Gold
(oz)
DSO
Mined
138,216
21.9
3.5
30,333
15,392
Crushed
139,355
22.0
3.5
30,656
15,569
DSO sales
118,245
25.2
3.2
29,764
12,140
Concentrator
Mined
794,760
5.1
1.7
40,779
43,320
Milled
561,743
4.8
1.8
26,901
32,513
Concentrate produced
84,663
23.1
3.8
19,594
10,225
Concentrate sold
67,390
22.9
3.6
15,434
7,872
Oxide gold
Mined
3,559
-
0.8
-
94
Milled (toll treatment)
78,571
-
3.7
-
9,270
Gold production
-
-
-
-
8,299
Gold sales
-
-
-
-
8,299
Total
Mined
936,535
7.6
2.0
71,112
58,806
Crushed/Milled
779,669
7.4
2.3
57,557
57,352
Copper production
224,018
22.4
3.6
50,250
25,794
Gold production
-
-
-
-
8,299
Contained metal
-
-
-
50,250
34,093
Copper and gold sales
185,635
24.3
-
45,198
28,311

Page: 23

Project to date
Tonnes
Grade (% Cu)
Grade (g/t Au)
Contained
Copper (t)
Contained Gold
(oz)
DSO
Mined
155,512
22.6
3.6
35,180
17,907
Crushed
155,512
22.6
3.6
35,180
17,907
DSO sales
124,735
25.7
3.2
32,012
13,015
Concentrator
Mined
823,892
5.1
1.7
42,121
44,315
Milled
561,743
4.8
1.8
26,901
32,513
Concentrate produced
84,663
23.1
3.8
19,594
10,225
Concentrate sold
67,390
22.9
3.6
15,434
7,872
Oxide gold
Mined
278,603
0.2
1.8
463
16,446
Milled (toll treatment)
87,121
-
3.7
-
10,255
Gold production
-
-
-
-
9,264
Gold sales
-
-
-
-
9,264
Total
Mined
1,258,007
6.2
1.9
77,764
78,668
Crushed/Milled
804,376
7.7
2.3
62,081
60,675
Copper production
240,175
22.8
3.6
54,774
28,132
Gold production
-
-
-
-
9,264
Contained metal
-
-
-
54,774
37,396
Copper and gold sales
192,125
24.7
-
47,446
30,151

Page: 24

  • C4 interpreted to be the faulted offset of C1

Fault plane trace

  • On this basis, DeGrussa (which is also truncated by the Shiraz Fault) should also have an offset equivalent

  • This exploration premise has opened up the area on the southern side of the Shiraz Fault – the “DeGrussa Offset Target”

Page: 25

==> picture [899 x 443] intentionally omitted <==

----- Start of picture text -----

SOUTH NORTH
WEST EAST OPEN PIT
DEGRUSSA
4m mineralised zone
OPEN PIT CONDUCTOR 1
8m mineralised zone
5.1m at 1.5% Cu
2.5m at 0.6% Cu
PRE-FAULTING
DEGRUSSA
1.4m at 0.3% Cu
CONDUCTOR 1
4.3m at 0.9% Cu CROSS
300m SECTION
5m & 2m mineralised zones
1.3m at 1.4% Cu
SOUTH NORTH
Current Hole
2.1m at 4.2% Cu CONDUCTOR 5
CONDUCTOR 4
DEGRUSSA
5.3m at 1.7% Cu OFFSET
TARGET
DEGRUSSA
HORIZON
OFFSET TARGET
4.0m at 1.1% Cu HORIZON
CONDUCTOR 4
LONGITUDINAL 0 200 400 600
SECTION metres
Previous Drill Program Intersection: Non-mineralised 300m
Previous Drill Program Intersection: Mineralised
Current Drill Program Intersection: Non-mineralised CROSS
Current Drill Program Intersection: Mineralised All widths are downhole SECTION
Current Drill Program Intersection: Assays pending True widths range from 30 – 60% of DH width
----- End of picture text -----

Page: 26

==> picture [809 x 390] intentionally omitted <==

  • Both Priority and Secondary Target Units consist of Dolerite + Basalt + Sediments

  • Footwall Unit consists of Conglomerate, Siltstone and Hematite Shales

Page: 27

  • Leverage off local knowledge

  • Understand broad basinal context

  • Target into coinciding ‘hot spots’

Page: 28

==> picture [889 x 393] intentionally omitted <==

  • Needs thorough analysis due to current anomaly size and strength

  • Current drilling still very wide spaced >400m x 100m

Page: 29