14 April 2016

==> picture [596 x 72] intentionally omitted <==

ASX Announcement

DEGRUSSA MINE PLAN, MINERAL RESOURCE AND ORE RESERVE UPDATE

Maiden C5 ore reserve and updated mine plan cements mine life to 2021

Highlights

Updated DeGrussa Mine Plan to 2021:

  • 8.1Mt grading 4.4% Cu and 1.7g/t Au for 357,000t of contained copper and 443,000oz of contained gold;

  • Mine production maintained at 1.6Mtpa rates; and

  • Mine development reducing.

Updated DeGrussa Underground Mineral Resource:

  • 7.8Mt grading 5.7% Cu and 2.1g/t Au for 443,000t of contained copper and 536,000oz of contained gold; and

  • Updated based on mining depletion, sterilisation and resource definition drilling.

  • Maiden Ore Reserve reported for the Conductor 5 deposit:

  • 1.8Mt grading 4.5% Cu and 2.1g/t Au for 83,000t of contained copper and 123,000oz of contained gold.

  • DeGrussa Ore Reserve update based on mining depletion and sterilisation as at 31 December 2015 – 10.8Mt grading 3.6% Cu and 1.5g/t Au for 388,000t of contained copper and 525,000oz of contained gold:

  • Underground Ore Reserve (including UG ore on surface stockpiles) – 8.0Mt grading 4.4% Cu and 1.7g/t Au for 353,000t of contained copper and 441,000oz of contained gold; and

  • Open Pit Ore Reserve (stockpiled at surface) – 2.8Mt grading 1.2% Cu and 1.0g/t Au for 35,000t of contained copper and 84,000oz of contained gold.

Sandfire Resources NL (ASX : SFR , “Sandfire”) is pleased to announce an updated Mine Plan, Mineral Resource and Ore Reserve as at 31 December 2015 for the 1.6 Mtpa DeGrussa CopperGold Mine.

The updated DeGrussa Mine Plan, Mineral Resource and Ore Reserve includes the DeGrussa, Conductor 1, Conductor 4 and Conductor 5 lenses, underpinning the mine life of the DeGrussa operation through until 2021. The updated Mineral Resource statement excludes the recently discovered Monty deposit, for which a maiden Indicated and Inferred Mineral Resource of 1.05Mt grading 9.4% Cu and 1.6g/t Au for 99,000t of contained copper and 55,000oz of contained gold was announced yesterday ( see ASX Announcement of 13 April 2016 ).

==> picture [596 x 36] intentionally omitted <==

Mine Plan

The Mine Plan is Sandfire’s internal plan which schedules forecasted production parameters, operating and capital works programs. It is developed with the assistance of both internal Sandfire employees and external consultants and includes both Mineral Resources and Ore Reserves.

Table 1 below compares the DeGrussa Mine Plan to the stated Mineral Resource and Ore Reserve by key output and mining tonnes (refer Appendix 1 for full details of the Mineral Resource and Ore Reserve).

The Company continues to incorporate Inferred Mineral Resources from portions of Conductor 1 and Conductor 5 into its Mine Plan process due to the geological continuity and high copper grade tenor of these deposits.

A zone of mineralisation associated with Conductor 5 adjacent to the Shiraz and Merlot Faults and the water-bearing dolomite unit has not been included in the Mineral Resource, Ore Reserve or Mine Plan. Further diamond drilling is required to assess the extent and nature of this mineralisation and the potential for mining. It is planned for this drilling to occur in early 2017 following commissioning of the Conductor 5 pump station.

Table 1 – December 2015 Comparison of the Underground Mine Plan, Mineral Resource and Ore Reserve

Tonnes Copper Gold Contained Contained
Contained
DeGrussa Underground Mine (Mt) (%) (g/t) Copper (t)
Gold (oz)
Mine Plan 8.1 4.4 1.7 357,000
443,000
Ore Reserve 8.0 4.4 1.7 353,000 441,000
Mineral Resource 7.8 5.7 2.1 443,000
536,000
DeGrussa Underground Mine by Tonnes Stockpiles DG C1 C4
C5
Orebody (Mt) (Mt) (Mt) (Mt) (Mt)
(Mt)
Mine Plan 8.1 0.1 0.9 3.1 2.2
1.8
Ore Reserve 8.0 0.1 0.9 3.0 2.2
1.8
Mineral Resource 7.8 0.1 0.9 3.0 2.1
1.7
  • Mine Plan and Ore Reserve include mining dilution and mining recovery.

Production has commenced from Conductor 4 with production rates planned to increase to the planned full rate of around 0.45Mtpa. Production from Conductor 5 is planned to commence in Q4 FY2016 with production rates increasing in FY2017.

The Mine Plan confirms underground mine production continuing at the current rate of 1.6 Mtpa. Mine development continues at around 6000m for FY2017, around 3000m for FY2018, and reduces to less than 1000m per year for the remainder of the Mine Plan.

FY2017 production is expected to be broadly in line with guidance previously provided for FY2016. Further guidance for FY2017 will be provided around the end of the June 2016 Quarter.

Mineral Resource Update

The DeGrussa Mineral Resource has been updated as at 31 December 2015 based on mining depletions, sterilisation and resource definition drilling, as set out in Table 2.

SANDFIRE RESOURCES NL

Page 2

Table 2 – December 2015 Mineral Resource

Tonnes Copper Gold Contained Contained
DeGrussa Mineral Resource (Mt) (%) (g/t) Copper (t) Gold (oz)
Underground Mine 7.8 5.7 2.1 443,000 536,000
Stockpiles(Open Cut) 2.9 1.2 1.0 35,000 89,000
December 2015 – Total 10.7 4.5 1.8 478,000 625,000

Ore Reserve Update

Diamond drilling and mine planning work has progressed sufficiently for the maiden Conductor 5 Ore Reserve to be reported as part of the DeGrussa Ore Reserve. The Conductor 5 Ore Reserve is 1.8Mt grading 4.5% Cu and 2.1g/t Au for 83,000t of contained copper and 123,000oz of contained gold.

Ore Reserves have been updated based on the December 2015 Mineral Resource model and depletions as at 31 December 2015, as set out in Table 3.

Table 3 – December 2015 Ore Reserve

Tonnes Copper Gold Contained Contained
DeGrussa Mine Ore Reserve (Mt) (%) (g/t) Copper (t) Gold (oz)
Underground Mine 8.0 4.4 1.7 353,000 441,000
Stockpiles(Open Cut) 2.8 1.2 1.0 35,000 84,000
December 2015 – Total 10.8 3.6 1.5 388,000 525,000

JORC Compliance Statement for Underground Mineral Resources and Ore Reserves

A summary of the information used in this release is as follows:

The DeGrussa VHMS (volcanic-hosted massive sulphide) copper-gold deposit is located 900 kilometres north of Perth and 150 kilometres north of Meekatharra in the Peak Hill Mineral Field. The system is hosted within a sequence of metasediments and mafic intrusions situated in the Bryah Basin that have been metamorphosed and structurally disrupted.

The sulphide mineralisation consists of massive sulphide and semi-massive sulphide mineralisation. Primary sulphide minerals present are pyrite, chalcopyrite, pyrrhotite and sphalerite, together with magnetite. The sulphide mineralisation is interpreted to be derived from volcanic activity. The deposit shares characteristics with numerous VHMS deposits worldwide.

DeGrussa is located wholly within Mining Lease 52/1046. This tenement is subject to the YugungaNya (WC99/046) and Gingirana Claims (WC06/002). A Land Access Agreement was executed with both claimant groups in November 2010. Sandfire is required to make royalty payments to the State and affected Native Title Claimants on a periodical basis.

Drilling of the DeGrussa massive sulphide lens (of which there are four defined lenses of mineralisation) and surrounding area is by diamond drill holes of NQ2 diameter core and, to a lesser extent, by Reverse Circulation (RC) face sampling hammer drilling. The nominal drill-hole spacing is less than 80m x 40m in the inferred areas of the Mineral Resource and increases in density as the classification increases to measured where nominal 13m x 20m drill hole spacing is achieved. Drilling has been by conventional diamond drilling with a small number holes aided by the use of navigational drilling tools. RC drilling was completed with a nominal 140mm face sampling hammer and split on a cone or riffle splitter. Drill-hole collar locations were surveyed using RTK GPS, and all holes were down-hole surveyed using high speed gyroscopic survey tools.

Sampling of diamond core was based on geological intervals (standard length 0.5 m to 1.3 m). The core was cut into half or quarter (NQ2) to give sample weights up to 3 kg. RC samples were 1.0m samples down-hole, with sample weights between 3.5kg and 7kg depending on material type. Field

SANDFIRE RESOURCES NL

Page 3

quality control procedures involved assay standards, along with blanks and duplicates. These QC samples were inserted at an average rate of 1:15.

The sample preparation of diamond core involved oven drying, coarse crushing of the core sample down to ~10 mm followed by pulverisation of the entire sample to a grind size of 90% passing 75 micron. A pulp sub-sample was collected for analysis by either four acid digest with an ICP/OES, ICP/MS (multi element) finish or formed into fused beads for XRF determination on base metals and a fire assay for Au.

All reported assays have been length weighted. No top-cuts have been applied. A nominal 0.3% Cu lower cut-off is applied. High grade intervals internal to broader zones of sulphide mineralisation are reported as included intervals.

The attitude of the ore bodies at DeGrussa is variable but there is a dominant southerly dip from ~40 to 90 degrees flat-lying and is drilled to grid west with drill holes inclined between -60 and -90 degrees. As such the dominant hole direction is north and with varying intersection angles all results are clearly defined as either down hole or approximate true width.

Density of the massive sulphide orebody ranges from 2.8g/cm3 to 4.9g/cm3, with an average density reading of 3.7g/cm3. Geotechnical and structural readings recorded from diamond drilling include recovery, RQD, structure type, dip, dip direction, alpha and beta angles, and descriptive information. All data is stored in the tables Oriented Structure, Geotechnical RQD, Core Recovery, Interval Structure as appropriate.

A suite of multi-element assays are completed on each mineralised sample and include all economic and typical deleterious elements in copper concentrates. This suite includes Cu, Au, Ag, Zn, Pb, S, Fe, Sb, Bi, Cd and As.

Open Pit Mineral Resources are quoted on a historical model and as such are compliant with the JORC 2004 guidelines.

ENDS

For further information contact: Sandfire Resources NL Read Corporate Karl Simich – Managing Director/CEO Mobile: +61 419 929 046 (Nicholas Read) Office: +61 8 6430 3800 Mobile: +61 421 619 084 (Paul Armstrong)

SANDFIRE RESOURCES NL

Page 4

Appendix 1 – Ore Reserve and Mineral Resource

DeGrussa Mine - Underground
As at 31 December 2015
Ore Reserve Mineral Resource*
Deposit Reserve
category
Tonnes
(Mt)
Copper
(%)
Gold
(g/t)
Contained
Copper (t)
Contained
Gold (oz)
Resource
category
Tonnes
(Mt)
Copper
(%)
Gold
(g/t)
Contained
Copper (t)
Contained
Gold (oz)
DeGrussa Proved
0.9
5.8
2.0
54,000
58,000
Probable
-
-
-
-
-
Measured
0.8
7.2
2.3
59,000
61,000
Indicated
<0.1
1.8
1.9
<1,000
1,000
Inferred
<0.1
6.2
3.0
<1,000
<1,000
Conductor 1 Proved
2.8
3.9
1.5
108,000
136,000
Probable
0.2
4.8
1.0
8,000
6,000
Measured
2.7
5.0
1.9
135,000
164,000
Indicated
0.2
5.7
1.6
10,000
10,000
Inferred
0.1
4.3
0.7
5,000
2,000
Conductor 4 Proved
0.9
3.7
1.7
33,000
49,000
Probable
1.3
4.9
1.6
61,000
64,000
Measured
1.7
5.8
2.0
100,000
112,000
Indicated
0.4
5.2
2.0
20,000
24,000
Inferred
<0.1
4.5
1.7
1,000
2,000
Conductor 5 Proved
-
-
-
-
-
Probable
1.8
4.5
2.1
83,000
123,000
Measured
1.0
6.4
2.9
66,000
97,000
Indicated
0.6
6.1
2.7
37,000
53,000
Inferred
0.1
7.4
2.9
4,000
5,000
Stockpiles Proved
0.1
4.4
1.3
6,000
5,000
Measured
0.1
4.4
1.3
5,000
5,000
Proved
4.7
4.2
1.6
201,000
248,000
Measured
6.4
5.7
2.1
366,000
439,000
Probable
3.3
4.7
1.8
152,000
193,000
Indicated
1.2
5.6
2.3
67,000
88,000
Inferred
0.2
5.1
1.5
10,000
9,000
Total
8.0
4.4
1.7
353,000
441,000
Total
7.8
5.7
2.1
443,000
536,000

SANDFIRE RESOURCES NL

Page 5

DeGrussa Mine – Open Pit
As at 31 December 2015
Ore Reserve Mineral Resource*
Deposit Reserve
category
Tonnes
(Mt)
Copper
(%)
Gold
(g/t)
Contained
Copper (t)
Contained
Gold (oz)
Resource
category
Tonnes
(Mt)
Copper
(%)
Gold
(g/t)
Contained
Copper (t)
Contained
Gold (oz)
Stockpiles Proved
2.8
1.2
1.0
35,000
84,000
Measured
2.8
1.2
1.0
35,000
84,000
Probable Indicated
0.2
0.2
1.1
<1,000
5,000
Inferred
-
-
-
-
-
Total
2.8
1.2
1.0
35,000
84,000
Total
2.9
1.2
1.0
35,000
89,000
DeGrussa Mine - Total
As at 31 December 2015
Ore Reserve Mineral Resource*
Deposit Reserve
category
Tonnes
(Mt)
Copper
(%)
Gold
(g/t)
Contained
Copper (t)
Contained
Gold (oz)
Resource
category
Tonnes
(Mt)
Copper
(%)
Gold
(g/t)
Contained
Copper (t)
Contained
Gold (oz)
DeGrussa Proved
0.9
5.8
2.0
54,000
58,000
Probable
-
-
-
-
-
Measured
0.8
7.2
2.3
59,000
61,000
Indicated
<0.1
1.8
1.9
<1,000
1,000
Inferred
<0.1
6.2
3.0
<1,000
<1,000
Conductor 1 Proved
2.8
3.9
1.5
108,000
136,000
Probable
0.2
4.8
1.0
8,000
6,000
Measured
2.7
5.0
1.9
135,000
164,000
Indicated
0.2
5.7
1.6
10,000
10,000
Inferred
0.1
4.3
0.7
5,000
2,000
Conductor 4 Proved
0.9
3.7
1.7
33,000
49,000
Probable
1.3
4.9
1.6
61,000
64,000
Measured
1.7
5.8
2.0
100,000
112,000
Indicated
0.4
5.2
2.0
20,000
24,000
Inferred
<0.1
4.5
1.7
1,000
2,000
Conductor 5 Proved
-
-
-
-
-
Probable
1.8
4.5
2.1
83,000
123,000
Measured
1.0
6.4
2.9
66,000
97,000
Indicated
0.6
6.1
2.7
37,000
53,000
Inferred
0.1
7.4
2.9
4,000
5,000
Stockpiles Proved
2.9
1.4
1.0
41,000
89,000
Measured
2.9
1.4
1.0
40,000
90,000
Indicated
0.2
0.2
1.1
<1,000
5,000
Proved
7.5
3.1
1.4
236,000
332,000
Measured
9.2
4.4
1.8
401,000
523,000
Probable
3.3
4.7
1.8
152,000
193,000
Indicated
1.4
5.0
2.2
68,000
94,000
Inferred
0.2
5.1
1.5
10,000
9,000
Total
10.8
3.6
1.5
388,000
525,000
Total
10.7
4.5
1.8
478,000
625,000
  • Calculations have been rounded to the nearest 1000 t, 0.1 % Cu grade and 1000 t Cu metal, 0.1 g/t Au grade, 1000 oz Au metal, differences may occur due to rounding.

SANDFIRE RESOURCES NL

Page 6

JORC 2012 MINERAL RESOURCE AND ORE RESERVES PARAMETERS DEGRUSSA COPPER MINE

Section 1: Sampling Techniques and Data

Criteria JORC Code Explanation Commentary
Sampling
techniques
Nature and quality of sampling (e.g. cut channels, random chips,
or specific specialised industry standard measurement tools
appropriate to the minerals under investigation, such as
downhole gamma sondes, or handheld XRF instruments, etc).
These examples should not be taken as limiting the broad
meaning of sampling.

The deposit is sampled by a combination of surface and underground
(UG) diamond drill (DD) and surface reverse circulation (RC) holes.

DD sampling include both half-core and quarter-core samples of NQ2
core size and RC samples are collected by a cone or riffle splitter using
a face sampling hammer with a nominal 140mm hole.
Include reference to measures taken to ensure sample
representivity
and
the
appropriate
calibration
of
any
measurement tools or systems used.

Sampling is guided by Sandfire DeGrussa protocols and Quality Control
(QC) procedures as per industry standard.
Aspects of the determination of mineralisation that are Material
to the Public Report.

The determination of mineralisation is based on observed amount of
sulphides and lithological differences.
In cases where ‘industry standard’ work has been done this
would be relatively simple (e.g. ‘reverse circulation drilling was
used to obtain 1 m samples from which 3 kg was pulverised to
produce a 30 g charge for fire assay’). In other cases more
explanation may be required, such as where there is coarse gold
that has inherent sampling problems. Unusual commodities or
mineralisation types (e.g. submarine nodules) may warrant
disclosure of detailed information.

DD sample is first crushed through a Jaques jaw crusher to -10mm,
then Boyd crushed to -4mm and pulverised via LM2 to nominal 90%
passing -75µm. RC samples are only Boyd crushed to -4mm and
pulverised to 90% passing -75µm.

A 0.4g assay charge is combined and fused into a glass bead with 9.0g
flux for XRF analysis. A 40g charge is used for Fire Assay.
Drilling
techniques
Drill type (e.g. core, reverse circulation, open-hole hammer,
rotary air blast, auger, Bangka, sonic, etc) and details (e.g. core
diameter, triple or standard tube, depth of diamond tails, face-
sampling bit or other type, whether core is oriented and if so, by
what method, etc).

The deposit was initially sampled by a combination of surface DD and
RC holes totalling 58,622m and 22,072m respectively that were used in
the Definitive Feasibility Study (DFS).

Subsequent to the DFS drilling, an additional 206,250m have been
completed for the Mineral Resource update of Conductor 1, DeGrussa,
Conductor 4 and Conductor 5 lodes comprising of
o169,750m of UG NQ2 DD grade control drilling,
o26,586m of UG Resource Definition and Extensional (ResDef)
drilling,
o6,200m of Surface ResDef drilling and
o3,714m of UG Geotech drilling.

All surface drill collars are surveyed using RTK GPS with downhole
surveying by gyroscopic methods except shallow RC holes.

All underground drill collars are surveyed usingTrimble S6 electronic

SANDFIRE RESOURCES NL

Page 7

theodolite. Downhole survey is completed by gyroscopic downhole
survey.

Holes are inclined at varying angles for optimal ore zone intersection.

All core where possible is oriented using a Reflex ACT II RD orientation
tool withstated accuracy of +/-1%intherange 0 to 88°.
Drill sample
recovery
Method of recording and assessing core and chip sample
recoveries and results assessed.

Diamond core recovery is logged and captured into the database with
weighted average core recoveries greater than 98%.

Surface RC sampling is good with almost no wet sampling in the mine
area.
Measures taken to maximise sample recovery and ensure
representative nature of the samples.

Core is meter marked and orientated to check against the driller’s
blocks, ensuring that all core loss is taken into account.

At the RC rig, sampling systems are routinely cleaned to minimise the
opportunity for contamination and drilling methods are focused on
sample quality.

Samples areroutinelyweighed and capturedinto the centraldatabase.
Whether a relationship exists between sample recovery and
grade and whether sample bias may have occurred due to
preferential loss/gain of fine/coarse material.

No sample recovery issues have impacted on potential sample bias.
Logging
Sub-sampling
techniques and
sample
preparation
Whether core and chip samples have been geologically and
geotechnically logged to a level of detail to support appropriate
Mineral Resource estimation, mining studies and metallurgical
studies.

Geological logging is completed for all holes and is representative
across the ore body. The lithology, alteration, and structural
characteristics of core are logged directly to a digital format following
standard procedures and using Sandfire DeGrussa geological codes.

Data is imported into the central database after validation in LogChief™.
Whether logging is qualitative or quantitative in nature. Core (or
costean, channel, etc) photography.

Logging is both qualitative and quantitative depending on the field being
logged.

Allcores are photographed.
The total length and percentage of the relevant intersections
logged.

All DD and RC drill holes are fully logged.
If core, whether cut or sawn and whether quarter, half or all core
taken.

Core orientation is completed where possible and all are marked prior to
sampling. Half core samples are produced using Almonte Core Saw.
Samples are weighed and recorded.

Some quarter core samples have been used and statistical test work
has shown them to be representative.
If non-core, whether riffled, tube sampled, rotary split, etc and
whether sampled wet or dry.

RC samples are split using a cone or riffle splitter.

A majority of RC samples are dry. On the occasion that wet samples
are encountered, they are dried priorto splittingwithariffle splitter.
For all sample types, the nature, quality and appropriateness of
the sample preparation technique.

Sample preparation at the onsite laboratory involves weighing and
drying the original sample at 80° for up to 24 hours. All DD Samples are
thencrushed throughJaques crushertonominal -10mm(for DDsample

SANDFIRE RESOURCES NL

Page 8

only) followed by a second stage crushing through Boyd crusher to
nominal -4mm. RC samples are only Boyd crushed to -4mm. Sample is
split to less than 2kg through linear splitter and excess retained for
metallurgical work. Sample splits are weighed at a frequency of 1:20
and entered into the job results file. Pulverising is completed using LM2
mill to 90% passing 75%µm. Pulp fines test is completed at a minimum
of 1:20. A 1.5kg of rock quartz is pulverised at rate of 1:20 samples.
Two lots of packets are retained for the onsite laboratory services whilst
the pulverised residue is shipped externally to Bureau Veritas laboratory
in Perth for further analysis.

Sample preparation at the Bureau Veritas laboratory in Perth involves
weighing and drying the original sample at 80° for up to 24 hours. DD
samples are first crushed through a Jaques crusher to nominal -10mm.
Second stage crushing is through Boyd crusher to a nominal -4mm. All
RC samples are only Boyd crushed to -4mm. Sample is then split to less
than 2kg through linear splitter and excess retained. Sample splits are
weighed at a frequency of 1:20 and entered into the job. Pulverising is
completed using LM5 mill to 90% passing 75%µm. Grind size checks
are completed at a minimum of 1 per batch. 1.5kg of rock quartz is
pulverised at every1:10 sample.
Quality control procedures adopted for all sub-sampling stages
to maximise representivity of samples.

Sandfire DeGrussa has protocols that cover auditing of sample
preparation at the laboratories and the collection and assessment of
data to ensure accurate steps in producing representative samples for
the analytical process. Key performance indices include contamination
index of 90% (that is 90% blanks pass); Crush Size index of P95-10mm;
Grind Size index of P90-75µm and Check Samples returning at worse
20% precision at 95% confidence interval and bias of 5% or better.

Weekly on-site laboratory audits are completed to ensure the laboratory
conforms to standards.

Additional grind size checks are completed via Umpire Checks.
Measures taken to ensure that the sampling is representative of
the in situ material collected, including for instance results for
field duplicate/second-half sampling.

Duplicate analysis has been completed and identified no issues with
sampling representatively.

Test work on half-core versus quarter-core has been completed with
results confirming that sampling at either core size is representative of
thein-situmaterial.
Whether sample sizes are appropriate to the grain size of the
material being sampled.

The sample size is considered appropriate for the Massive Sulphide
mineralisation style.
Quality of assay
data and
laboratory tests
The nature, quality and appropriateness of the assaying and
laboratory procedures used and whether the technique is
considered partial or total.

At the onsite laboratory, a 0.4g sub-sample with 9.0g flux is fused into a
glass bead. XRF method is used to analyse for a suite of elements
(including Cu, Fe, SiO2, Al, Ca, MgO, P, Ti, Mn, Co, Ni, Zn, As, and Pb).

SANDFIRE RESOURCES NL

Page 9

Pulps are dispatched to Bureau Veritas laboratory in Perth for ICPOES
or ICPMS for extended elements (including Cu, Fe, As, Pb, S, Zn, Fe,
Ag, Sb, Bi, Cd, Cl, F, and Hg).

Samples submitted to Bureau Veritas laboratory in Perth are assayed
using Mixed 4 Acid Digest (MAD) 0.3g charge and MAD Hotbox 0.15g
charge methods with ICPOES or ICPMS. The samples are digested and
refluxed with a mixture of acids including Hydrofluoric, Nitric,
Hydrochloric and Perchloric acids and conducted for multi elements
including Cu, Pb, Zn, Ag, As, Fe, S, Sb, Bi, Mo, Re, Mn, Co, Cd, Cr, Ni,
Se, Te, Ti, Zr, V, Sn, W and Ba. The MAD Hotbox method is an
extended digest method that approaches a total digest for many
elements however some refractory minerals are not completely
attacked. The elements S, Cu, Zn, Co, Fe, Ca, Mg, Mn, Ni, Cr, Ti, K, Na,
V are determined by ICPOES, and Ag, Pb, As, Sb, Bi, Cd, Se, Te, Mo,
Re, Zr, Ba, Sn, W are determined by ICPMS. Samples are analysed for
Au, Pd and Pt by firing a 40g portion of the sample. Au, Pd and Pt are
determined by ICPOES. Lower sample weights are employed where
samples have very high S contents.

These analytical methods are considered appropriate for the
mineralisation style.
For
geophysical
tools,
spectrometers,
handheld
XRF
instruments, etc, the parameters used in determining the
analysis including instrument make and model, reading times,
calibrations factors applied and their derivation, etc.

Handheld XRF units are used as grade control tools to delineate ore
boundaries and grades in the field and for exploration for alteration
minerals. These units are fit for this purpose. Handheld XRF results are
not used in the Mineral Resource estimation.
Nature of quality control procedures adopted (e.g. standards,
blanks, duplicates, external laboratory checks) and whether
acceptable levels of accuracy (i.e. lack of bias) and precision
have been established.

Sandfire DeGrussa Quality Control (QC) protocol is considered industry
standard with standard reference material (SRM) submitted on regular
basis with routine samples.

SRMs and blanks are inserted at a minimum of 5% frequency rate. A
minimum of 2% of assays are routinely re-submitted as Check Assays
and Check Samples through blind submittals to external and the onsite
primary laboratories respectively. Additionally, Umpire Checks are
completed on quarterly basis.

QC data returned is automatically checked against set pass/fail limits
within SQL database and are either passed or failed on import. On
import a first pass automatic QC report is generated and sent to QAQC
Geologists for recommended action. Results of all QC samples for every
laboratory batch received are analysed to determine assay accuracy
and repeatability.

Only data that demonstrate sufficient accuracy and precision of assays
are usedfor Mineral Resource updates.

SANDFIRE RESOURCES NL

Page 10

Verification of
sampling and
assaying
The verification of significant intersections by either independent
or alternative company personnel.

Significant intersections have been verified by alternative company
personnel.
The use of twinned holes.
There are no twinned holes drilled for the DeGrussa Mineral Resource.
Documentation of primary data, data entry procedures, data
verification, data storage (physical and electronic) protocols.

Primary data are captured on field tough book laptops using Logchief™
Software. The software has validation routines and data is then
importedinto a secure centraldatabase.
Discuss any adjustment to assay data.
The primary data is always kept and is never replaced by adjusted or
interpreted data.
Location of data
points
Accuracy and quality of surveys used to locate drill holes (collar
and down-hole surveys), trenches, mine workings and other
locations used in Mineral Resource estimation.

Sandfire DeGrussa Survey team undertakes survey works under the
guidelines of best industry practice.

All surface drill collars are accurately surveyed using RTK GPS system
within +/-50mm of accuracy (X, Y, Z) with no coordinate transformation
applied to the picked up data.

There is a GPS base station onsite that has been located by a static
GPS survey from two government standard survey marks (SSM)
recommended by Landgate. Downhole survey is completed by
gyroscopic downhole methods at regular intervals.

Underground drilling collar surveys are carried out using Trimble S6
electronic theodolite and wall station survey control. Re-traverse is
carried out every 100 vertical meters within main decline. Downhole
surveys are completed by gyroscopic downhole methods at regular
intervals.
Specification of the grid system used.
MGA94 Zone 50 grid coordinate system is used.
Quality and adequacy of topographic control
A 1m ground resolution DTM with an accuracy of 0.1m was collected by
Digital Mapping Australia using LiDAR and a vertical medium format
digital camera (Hasselblad). The LiDAR DTM and aerial imagery were
used to produce a 0.1m resolution orthophoto that has been used for
subsequent planning purposes.
Data spacing
and distribution
Data spacing for reporting of Exploration Results.
No Exploration Results are included in this release.
Whether the data spacing and distribution is sufficient to
establish the degree of geological and grade continuity
appropriate for the Mineral Resource and Ore Reserve
estimation procedure(s) and classifications applied.

Data spacing and distribution are sufficient to establish the degree of
geological and grade continuity appropriate for the JORC 2012
classifications applied.
Whether sample compositing has been applied.
No sample compositing is applied during the sampling process.

SANDFIRE RESOURCES NL

Page 11

Orientation of
data in relation
to geological
structure
Whether the orientation of sampling achieves unbiased sampling
of possible structures and the extent to which this is known,
considering the deposit type.

The majority of the drillholes are orientated to achieve intersection
angles as close to perpendicular to the mineralisation as practicable.
If the relationship between the drilling orientation and the
orientation of key mineralised structures is considered to have
introduced a sampling bias, this should be assessed and
reported if material

No significant sampling bias occurs in the data due to the orientation of
drilling with regards to mineralised bodies.
Sample security The measures taken to ensure sample security.
Chain of custody of samples is being managed by Sandfire Resources
NL.

Appropriate security measures are taken to dispatch samples to the
laboratory. Samples are transported to the external laboratory by Toll
IPEC or Nexus transport companies in sealed bulka bags.

The laboratory receipt received samples against the sample dispatch
documents and issues a reconciliation report for every sample batch.

Laboratory dumps the excess material (residue) after 30 days unless
instructed otherwise.

Laboratory returns all pulp samples within 60 days.
Audits or
reviews
The results of any audits or reviews of sampling techniques and
data.

The sampling techniques and data collection processes are of industry
standard and have been subjected to multiple internal and external
reviews. Cube Consulting Pty completed a review during 18th- 20th
February 2014 and found procedures to be consistent with industry
standard and appropriate with minor recommendations for
enhancement as part ofcontinuousimprovement.

Section 2: Not applicable

SANDFIRE RESOURCES NL

Page 12

Section 3: Estimation and Reporting of Mineral Resources

Criteria JORC Code Explanation Commentary
Database
integrity
Measures taken to ensure that data has not been corrupted by,
for example, transcription or keying errors, between its initial
collection and its use for Mineral Resource estimation purposes.

Sandfire uses SQL as the central data storage system via Datashed™
software front end. User access to the database is regulated by specific
user permissions. Only the Database Management team can overwrite
data.

Existing protocols maximise data functionality and quality whilst
minimising the likelihood of error introduction at primary data collection
points and subsequent database upload, storage and retrieval points.

Data templates with lookup tables and fixed formatting are used for
collecting primary data on field Toughbook laptops. The software has
validation routines and data is subsequently imported into a secure
central database.

An IT contracting company is responsible for the daily Server backups
of both the source file data on the file server and the SQL Server
databases. The selected SQL databases are backed up to disk with
“Backup Exec” each day and then transferred to tape for long term
storage. This allows for a full recovery.
Data validation procedures used.
The SQL server database is configured for optimal validation through
constraints, library tables, triggers and stored procedures. Data that fails
these rules on import is rejected or quarantined until it is corrected.

Database is centrally managed by a Database Manager who is
responsible for all aspects of data entry, validation, development, quality
control and specialist queries.

There is a standard suite of vigorous validation checks for all data.
Site Visits Comment on any site visits undertaken by the Competent
Person and the outcome of those visits.

The Competent Person for this Mineral Resource update is a full time
employee of Sandfire Resources NL and undertakes regular site visits.
If no site visits have been undertaken indicate why this is the
case.

Sites visits are undertaken.
Geological
interpretation
Confidence in (or conversely, the uncertainty of) the geological
interpretation of the mineral deposit.

Interpretation is based on geological knowledge acquired through data
acquisition from the open pit and underground workings, including
detailed geological core and chip logging, assay data, underground
development face mapping of orebody contacts and in-pit mapping. This
information increases the confidence in the interpretation of the deposit.

SANDFIRE RESOURCES NL

Page 13

Criteria JORC Code Explanation Commentary
Nature of the data used and of any assumptions made.
All available geological logging data from diamond core and reverse
circulation drilling are used for the interpretations.

Interpreted fault planes have been used to constrain the wireframes
where applicable.

All development drives are mapped and surveyed and interpretation
adjusted as per ore contacts mapped.

Wireframes are constructed using cross sectional interpretations based
on logged massive sulphides in combination with Cu, Fe and S
analyses.
The effect, if any, of alternative interpretations on Mineral
Resource estimation.

The geological interpretation of mineralised boundaries are considered
robust and alternative interpretations do not have the potential to impact
significantly on the Mineral Resources. Ongoing site and coporate peer
reviews, and external reviews, ensure that the geological interpretation
is robust.
The use of geology in guiding and controlling Mineral Resource
estimation.

The interpreted mineralisation boundaries are used as hard boundaries
during the Mineral Resource estimation.
The factors affecting continuity both of grade and geology.
Sandfire DeGrussa Copper Mine mineralisation style, chemistry and
regional setting are consistent with volcanogenic sulphide style deposit.
The primary sulphide mineralisation consists of massive sulphide, semi-
massive sulphide and more rarely, stringer mineralisation. Gold is
associated with the chalcopyrite rich phases and occurs as a high silver
electrum. Mineralisation terminates at known faults.
Dimensions The extent and variability of the Mineral Resource expressed as
length (along strike or otherwise), plan width, and depth below
surface to the upper and lower limits of the Mineral Resource.

All known DeGrussa deposit mineralisation extends from 733500mE to
734785mE, 7172965mN to 7173590mN and 650m below surface.

The DeGrussa sulphide lode generally strikes towards NE with a strike
length of approximately 210m, dipping very steeply towards the south
with a SSE subtle plunge and having a vertical extent of about 200m.

The Conductor 1 lode lies north of DeGrussa and generally strikes NE
dipping generally at 70° to the SW. It has a strike length of about 400m
with a vertical extent of 370m plunging to SE at about 15°.

Conductor 4 lenses lie to the east of DeGrussa and Conductor1 lodes
and are stratigraphically deeper. Strike length is up to 510m with dips
varying between 35°- 45° to the SE and a vertical extent of 3500m

Conductor 5 lenses are east of Conductor 4 and have strike length up to
280m meter strike length dipping at about 45° to the south-southwest,
and a vertical extent of 370m.

SANDFIRE RESOURCES NL

Page 14

Criteria JORC Code Explanation Commentary
Estimation and
modelling
techniques
The nature and appropriateness of the estimation technique(s)
applied and key assumptions, including treatment of extreme
grade
values,
domaining,
interpolation
parameters
and
maximum distance of extrapolation from data points. If a
computer assisted estimation method was chosen include a
description of computer software and parameters used.

Mineral Resource estimation is completed within Datamine™ Studio 3
Resource
Modelling
software. Three
dimensional mineralisation
wireframes are completed within Surpac™ or Leapfrog™ software and
then imported into Datamine™.

With the exception of Au, geostatistical ordinary kriging (OK) using
dynamic local anisotropic search is used to estimate the Mineral
Resource as it is considered appropriate given the nature of
mineralisation and orebody configuration.

Gold is estimated using Indicator Kriging (IK).

The Mineral Resource database is uniquely flagged with mineralisation
zone codes as defined by wireframe boundaries and then composited
into density weighted 1m lengths and these are used for estimating the
Mineral Resource. The composites are extracted with minimum passing
of 70% and best fit such that no residuals are created.

Statistical and geostatistical analysis are undertaken within Snowden’s
Supervisor™ software.

Histograms, log-probability plots and mean variance plots are
considered in determining the appropriate cut-offs for each mineralised
zone. The points of inflexion in the upper tail of the distribution on the
log-probability plots as well as their spatial distributions are examined to
help identify outliers and decide on the treatments applied. High-grade
cuts used are either as top-cuts or high grade spatial restriction or a
combination of both. All grade values greater than the cut-off grade are
set to the cut-off value (capped).

Variography studies includes analysing series of fans in three principal
directions of horizontal, across-strike vertical and dip planes. The
selected strike, plunge and dip directions are used to locate the three
directions for which experimental variogram models are fitted. The
nugget variance is modelled first by the use of down-hole variograms
based on 1m lag, reflecting the downhole composite spacing.
Variograms are estimated by fitting spherical models in the three
principal directions using the nugget variance modelled for the same
mineralised zone.

Quantitative Kriging Neighbourhood Analysis (QKNA) using the
goodness of fit statistics to optimise estimation parameters is
undertaken.

Elements estimated include Cu, Au, Ag, Fe, S, Pb, and Zn.

SANDFIRE RESOURCES NL

Page 15

Criteria JORC Code Explanation Commentary
The availability of check estimates, previous estimates and/or
mine production records and whether the Mineral Resource
estimate takes appropriate account of such data.

The new estimates have been checked against the previous estimates.

The current Mineral Resource takes into account mine production using
wireframe of the mined out open pit outline and CMS data for
undergroundmined out areas.
The assumptions made regarding recovery of by-products.
No assumptions are made regarding recovery of by-products during the
Mineral Resource estimation.
Estimation of deleterious elements or other non-grade variables
of economic significance (e.g. sulphur for acid mine drainage
characterisation).

Estimates includes deleterious or penalty elements Pb, Bi, Zn, As, MgO
as well as Pyrite:Pyrrhotite ratio for metallurgical modelling.
In the case of block model interpolation, the block size in relation
to the average sample spacing and the search employed.

Estimation is based on interpolation into three dimensional parent blocks
of sizes X=5m by Y=5m by Z=5m within close spaced (GC) drilling areas
where ore body drillhole intercept spacing varies from 0.2m to 45m
averaging at 6m. Within the ResDef areas, parent block sizes of X=10m
by Y=10m by Z=10 are considered adequate for drillhole intercept
spacing varying from 8m to 90m and averaging 30m. All parent blocks
have been sub-blocked into X=1m by Y=1m by Z=1m sizes. Parent
block evaluations are assigned to sub-blocks.

Given that the orientation of mineralisation varies considerably within the
DeGrussa deposit and to preserve the orientation of mineralisation,
“Dynamic Anisotropy” option of Datamine Studio3™ is used. This option,
allows orienting the search volume precisely such that it follows the
trend of the mineralisation.

Directional ranges are determined from variogram modelling and are
used to constrain the search distances used in the block interpolation.
To preserve local grade variation, the search neighborhood strategy
implemented involves the use of three estimation search runs with initial
short-search set to approximately 75% of the variogram range for the
respective element and extending the sample influence in later runs. To
estimate a block, data from more than one drillhole is used; a minimum
of 6/8 and maximum 30 composites are used with no more than 4
composites from a single drill-hole.

High grade restriction is sometimes used to ensure that only blocks with
centroids within a search radius corresponding to the first pass of a
designated high-grade are estimated with composites including the high
grades. Any block whose centroid is outside this limit is estimated with
composites excluding thehighgrades.
Any assumptions behind modelling of selective mining units.
No selective mining units are assumed in this estimate.

SANDFIRE RESOURCES NL

Page 16

Criteria JORC Code Explanation Commentary
Any assumptions about correlation between variables.
Within the massive sulphides there is a good and consistent correlation
between Fe and S and density which has been analysed separately for
all lodes using multiple regression to fit the density, Fe and S
relationship. The regressed formula is then applied to block model
estimated Fe and S to assign the estimated block density value.
Description of how the geological interpretation was used to
control the resource estimates.

The mineralogy interpretation wireframes correlate with the massive
sulphide mineralisation boundaries. The block model is assigned unique
mineralisation zone codes that corresponds with the mineralogical
domain as defined by wireframes. The mineralogical interpretations are
then used as hard boundaries during interpolation where blocks are
estimated only with composites having the corresponding zone code.
Discussion of basis for using or not using grade cutting or
capping.

Statistical analysis in conjunction with the examination of the spatial
configuration of samples are used to assist in identifying outliers and
decide on the treatments applied. High-grade cuts strategy used is
either as a top-cut or high grade spatial restriction or a combination of
both to minimise the smoothing of very high-grades in areas not
supported by data.
The process of validation, the checking process used, the
comparison of model data to drill hole data, and use of
reconciliation data if available.

The process of validation includes standard model validation using
visual and numerical methods:
o
The block model estimates are checked against the input
composite/drillhole data with sufficient spot checks completed on
sections and plans.
o
The block model estimated global means for each mineralised
domain are checked against the declustered composite mean
grades to ensure they are within acceptable variance.
o
Efficiency models using block Kriging Efficiencies (KE) and Slope of
Regression (ZZ) are used to quantitatively check the estimation
quality.
o
Swath plots of the estimated block grades and composite mean
grades are generated by eastings, northings and elevations and
reviewed to ensure acceptable correlation.
o
Peer reviews.

Reconciled production data verse Mineral Resource estimate is
satisfactory.

SANDFIRE RESOURCES NL

Page 17

Criteria JORC Code Explanation Commentary
Moisture Whether the tonnages are estimated on a dry basis or with
natural moisture, and the method of determination of the
moisture content.

Tonnages are estimated on a dry basis.
Cut-off
parameters
The basis of the adopted cut-off grade(s) or quality parameters
applied.

Based upon data review a notional lower cut-offs of 0.3% Cu for Oxides
Copper and 1.0% Cu for Massive Sulphides appear to be a natural
grade boundary between ore and trace assay values.
Mining factors
or assumptions
Assumptions
made
regarding
possible
mining
methods,
minimum mining dimensions and internal (or, if applicable,
external) mining dilution. It is always necessary as part of the
process of determining reasonable prospects for eventual
economic extraction to consider potential mining methods, but
the
assumptions
made
regarding
mining
methods
and
parameters when estimating Mineral Resources may not always
be rigorous. Where this is the case, this should be reported with
an explanation of the basis of the mining assumptions made.

The upper portion of the DeGrussa deposit was mined by open pit and
completed in two stages. The approximate dimensions of the open pit at
completion were 600m length, 500m wide and 140m deep. Open pit
mining comprised of conventional backhoe excavator methods with ore
being mined in 5m benches on 2.5m flitches.

Primary mining methods employed are sub-level open stoping (SLOS)
and long-hole open stoping (LHOS) with fill. Primary fill material is paste
with minor use of cemented rock fill and rock fill when appropriate.

Detailed mine plans are in place and mining is occurring.
Metallurgical
factors or
assumptions
The basis for assumptions or predictions regarding metallurgical
amenability. It is always necessary as part of the process of
determining reasonable prospects for eventual economic
extraction to consider potential metallurgical methods, but the
assumptions regarding metallurgical treatment processes and
parameters made when reporting Mineral Resources may not
always be rigorous. Where this is the case, this should be
reported with an explanation of the basis of the metallurgical
assumptions made.

Sulphide mineralisation consists of massive sulphide, semi-massive
sulphide and minor stringer zone mineralisation. Distinct iron sulphide
mineralogy (and quantity) tends to define metallurgical response.
Properties within the different ore types are relatively consistent across
the ore bodies and appear to follow similar comminution parameters and
flotation responses. The sulphide minerals are amenable to recovery by
flotation. The dominant valuable component is copper, which is
contained predominantly in chalcopyrite with minor assemblages of
chalcocite mineralisation.

Assumptions are based on DFS metallurgical test work and ongoing
monitoring of the DeGrussa processing plant ramp up.

Target recovery is 90% of Cu.

SANDFIRE RESOURCES NL

Page 18

Criteria JORC Code Explanation Commentary
Environmental
factors or
assumptions
Assumptions made regarding possible waste and process
residue disposal options. It is always necessary as part of the
process of determining reasonable prospects for eventual
economic extraction to consider the potential environmental
impacts of the mining and processing operation. While at this
stage the determination of potential environmental impacts,
particularly for a greenfields project, may not always be well
advanced, the status of early consideration of these potential
environmental impacts should be reported. Where these aspects
have not been considered this should be reported with an
explanation of the environmental assumptions made.

The DeGrussa project is constructed with a fully lined Tailings Storage
Facility and all Sulphide material mined from the operation will be
processed in the concentrator, eliminating any PAF on the waste
dumps.
Bulk density Whether assumed or determined. If assumed, the basis for the
assumptions. If determined, the method used, whether wet or
dry, the frequency of the measurements, the nature, size and
representativeness of the samples.

Water immersion is the current methodology used in the measurement
of densities. Regular and systematic density measurements are taken
on representative number of diamond drill core according to a formal
protocol. This data is included in the database. Within the massive
sulphides bulk density varies from 2.8_g/cm3_to 4.9_g/cm3_, with an
average density reading of 3.7_g/cm3_. Average density of 2.8 is
assigned to waste blocks.

To test the methodology and accuracy of the density measurements,
regular samples constituting 20% of total measurements are submitted
to an independent laboratory for measurements.
The bulk density for bulk material must have been measured by
methods that adequately account for void spaces (vugs,
porosity, etc), moisture and differences between rock and
alteration zones within the deposit.

The procedure used is suitable for non-porous or very low porosity
samples, which can be quickly weighed in water before saturation
occurs.

SANDFIRE RESOURCES NL

Page 19

Criteria JORC Code Explanation Commentary
Discuss assumptions for bulk density estimates used in the
evaluation process of the different materials

Densities vary within the massive sulphides mineralisation and have
consistent correlation with Fe and S. Regressed formula of density is
used to calculate densities into blocks based on block estimated Fe and
S.

The host volcanic and sedimentary rocks are assigned an average
density value of 2.8_g/cm3_consistent with measurements.

Statistical analysis has shown that within the mineralised lenses
pyrite/pyrrhotite
dominant
versus
mixed
mineralisation/lithologies
constitute distinct statistical density sub-populations. The logged
pyrite/pyrrhotite percentage greater than 70% are typically consistent
with homogenous massive sulphides zones within the mineralised
lenses. Outside these areas are the mixed mineralisation zones which
consist of semi-massive sulphides with interbedded volcanic rocks or
carbonate/chloride
alterations.
These
density
sub-domains
are
demarcated using geostatistical categorical kriging estimation method
based on the logged pyrite/pyrrhotite percentage values. The density,
Fe and S relationships are then fitted separately for each sub-domain
and are then applied to the block model estimated Fe and S to assign
the estimated block density values.
Classification The basis for the classification of the Mineral Resources into
varying confidence categories.

The Mineral Resources has been classified into Measured, Indicated
and Inferred categories following the guidelines of the Australasian
Code for Reporting of Exploration Results, Mineral Resources and Ore
Reserves (JORC Code 2012). The classification is based on drill hole
intercept
spacing,
geological
confidence,
grade
continuity
and
estimation quality. A combination of these factors guides the manual
digitising of strings on drill sections to construct envelopes that are used
to control the Mineral Resource classification. This process allows
review of the geological control/confidence on the deposit. Measured
Resources are areas within drill hole intercept spacing of 20m by 20m
and estimated with a minimum of 8 samples with no more than 4
samples from any single drillhole. Indicated Mineral Resources are
areas within drill hole intercept spacing of 40m by 40m, estimated with
minimum 6 samples with no more than 4 samples from a single drillhole.
Whether appropriate account has been taken of all relevant
factors (i.e. relative confidence in tonnage/grade estimations,
reliability of input data, confidence in continuity of geology and
metal values, quality, quantity and distribution of the data).

The Mineral Resource classification has appropriately taken into
account data spacing, distribution, reliability, quality and quantity of input
data as well as the confidence in predicting grade and geological
continuity.

SANDFIRE RESOURCES NL

Page 20

Criteria JORC Code Explanation Commentary
Whether the result appropriately reflects the Competent
Person’s view of the deposit.

The Mineral Resource estimation appropriately reflects the Competent
Person’s view of the deposit.
Audits or
reviews
The results of any audits or reviews of Mineral Resource
estimates.

The DeGrussa Database has been subject to an independent data and
assay audit. Maxwell Geoservices completed an audit in January 2016
and found the SQL database to be of industry standard, with minor
issues noted such as unmatched data, missing data and noted minor
schema limitations.

The process for geological modelling, estimation and reporting of
Mineral Resources is industry standard and has been subject to an
independent external review. Cube Consulting Pty undertook a review of
the estimation in January 2016 and found the process to be of industry
standard with some low risk issues noted.
Discussion of
relative
accuracy/
confidence
Where appropriate a statement of the relative accuracy and
confidence level in the Mineral Resource estimate using an
approach or procedure deemed appropriate by the Competent
Person.
For
example,
the
application
of
statistical
or
geostatistical procedures to quantify the relative accuracy of the
resource within stated confidence limits, or, if such an approach
is not deemed appropriate, a qualitative discussion of the factors
that could affect the relative accuracy and confidence of the
estimate.

The Mineral Resources has been reported in accordance with the
guidelines of the 2012 edition of the Australasian Code for Reporting of
Exploration Results, Mineral Resources and Ore Reserves and reflects
the relative accuracy of the Mineral Resources estimates.
The statement should specify whether it relates to global or local
estimates, and, if local, state the relevant tonnages, which
should be relevant to technical and economic evaluation.
Documentation should include assumptions made and the
procedures used.

The statements relates to global estimates of tonnes and grade.
These statements of relative accuracy and confidence of the
estimate should be compared with production data, where
available.

Reconciled production data verse Mineral Resource estimate is
satisfactory.

SANDFIRE RESOURCES NL

Page 21

Section 4: Estimation and Reporting of Ore Reserves

Criteria JORC Code Explanation Commentary
Mineral
Resource
estimate for
conversion to
Ore Reserves
Description of the Mineral Resource estimate used as a basis for
the conversion to an Ore Reserve.
The Underground Ore Reserves estimate is based on the Mineral
Resources estimate as at the 31 December 2015. The estimation and
reporting of Mineral Resources is outlined in Section 3 of this Table.
Clear statement as to whether the Mineral Resources are
reported additional to, or inclusive of, the Ore Reserves.
Mineral Resources are reported inclusive of Ore Reserves.
Site visits Comment on any site visits undertaken by the Competent
Person and the outcome of those visits.
The Competent Person for this Mineral Resource update is a full time
employee of Sandfire Resources NL and undertakes regular site visits.
If no site visits have been undertaken indicate why this is the
case.
Site visits are undertaken as described above.
Study status The type and level of study undertaken to enable Mineral
Resources to be converted to Ore Reserves.
The DeGrussa mine has been in operation since 2011. Underground
stope production commenced in October 2012. The Modifying Factors
used in the conversion of Mineral Resources to Ore Reserves are based
on operational experience.
Cut-off
parameters
The basis of the cut-off grade(s) or quality parameters applied. Three break-even grades have been calculated and applied as
economic cut-offs in the determination of the Ore Reserves. These are
based on current and forecasted costs, revenues, mill recoveries and
modifying factors, forecast for the life of the mine plan. These cut-off
values are:
oFull cost break-even – is based on all operating costs associated with
the production of copper metal;
oIncremental break-even - considers material below the full cost
break-even that is accessible; and
oMill break-even – considers material that has to be mined in the
process of gaining access to fully costed economic material.
Mining factors
or assumptions
The method and assumptions used as reported in the Pre-
Feasibility or Feasibility Study to convert the Mineral Resource
to an Ore Reserve (i.e. either by application of appropriate
factors by optimisation or by preliminary or detailed design).
Ore Reserves have been estimated by generating detailed mining
shapes for all areas that contain Measured or Indicated Mineral
Resources as well as access development. Internal stope dilution has
been designed into the mining shapes and interrogated. External stope
dilution and mining recovery factors have been applied post geological
interrogation to generate final diluted and recovered ore.

SANDFIRE RESOURCES NL

Page 22

Criteria JORC Code Explanation Commentary
The choice, nature and appropriateness of the selected mining
method(s) and other mining parameters including associated
design issues such as pre-strip, access, etc.
Primary mining methods employed are sub-level open stoping (SLOS)
and long-hole open stoping (LHOS) with fill. Primary fill material is paste
with minor use of cemented rock fill and rock fill when appropriate.
The selected mining methods are considered appropriate for the nature
of the defined Mineral Resources.
The assumptions made regarding geotechnical parameters (eg
pit slopes, stope sizes, etc), grade control and pre-production
drilling.
Stopes to be mined in the short term are assessed on an individual basis
using all related local mining, geological and geotechnical experience to
date. This includes data gathered from back-analysis of stopes mined to
date in adjacent or similar areas.
Stopes to be mined in the medium to long term employ geotechnical
parameters derived from area mining experience and / or diamond drill
core.
The major assumptions made and Mineral Resource model used
for pit and stope optimisation (if appropriate).
The Mineral Resource model created to estimate the Mineral Resources
as at the 31 December 2015 was used as the basis for stope and
development design. No modifications were made to this model for mine
design purposes.
The mining dilution factors used. An external dilution factor is applied to stopes on an individual basis.
The factor is based on mining experience to date and ranges from 10 %
to 15 % dependent on mining area. External dilution is considered at
zero grade.
The mining recovery factors used. A mining recovery factor is applied to stopes on an individual basis. The
factor is based on mining experience to date and ranges from 95 % to
100 %. The factor is applied to diluted stopes.
Any minimum mining widths used. DeGrussa does not in general use a minimum mining width due to the
nature of the deposit.
The manner in which Inferred Mineral Resources are utilised in
mining studies and the sensitivity of the outcome to their
inclusion.
The Underground Ore Reserves contain approximately 0.1 % of Inferred
Mineral Resource. No modfications have been made to this material. Its
inclusion and subsequent impact on economic viability is considered
negligible.
The infrastructure requirements of the selected mining methods. DeGrussa is an operating mine and all infrastructure required to service
the selected mining methods is in place.

SANDFIRE RESOURCES NL

Page 23

Criteria JORC Code Explanation Commentary
Metallurgical
factors or
assumptions
The metallurgical process proposed and the appropriateness of
that process to the style of mineralisation.
Whether the metallurgical process is well-tested technology or
novel in nature.
The nature, amount and representativeness of metallurgical test
work undertaken, the nature of the metallurgical domaining
applied and the corresponding metallurgical recovery factors
applied.
Any assumptions or allowances made for deleterious elements.
The existence of any bulk sample or pilot scale test work and the
degree to which such samples are considered representative of
the orebody as a whole.
For minerals that are defined by a specification, has the ore
reserve estimation been based on the appropriate mineralogy to
meet the specifications?
The Ore Reserve estimate is based on an operating 1.6 Mtpa process
plant producing a 24.5% copper-concentrate that contains gold and
silver.

The Cu recovery algorithm used in the determination of the Ore Reserve
estimate is Cu Recovery = 0.08072 * LN ( Ore Grade Cu / Ore Grade S )
+ 1.0423.

Au and Ag recovery are both 45%.

Process improvement projects are being investigated in FY16 to further
debottleneck the mill and provide improved recovery.
Environmental The status of studies of potential environmental impacts of the
mining and processing operation. Details of waste rock
characterisation and the consideration of potential sites, status
of design options considered and, where applicable, the status
of approvals for process residue storage and waste dumps
should be reported.
DeGrussa is an operating mine and is compliant with all environmental
regulatory requirements and permits.
Infrastructure The existence of appropriate infrastructure: availability of land for
plant development, power, water, transportation (particularly for
bulk commodities), labour, accommodation; or the ease with
which the infrastructure can be provided, or accessed.
DeGrussa is an operating mine and all infrastructure required for
continued operation is in place.

SANDFIRE RESOURCES NL

Page 24

Criteria JORC Code Explanation Commentary
Costs The derivation of, or assumptions made, regarding projected
capital costs in the study.
The methodology used to estimate operating costs.
Allowances made for the content of deleterious elements.
The source of exchange rates used in the study.
Derivation of transportation charges.
The basis for forecasting or source of treatment and refining
charges, penalties for failure to meet specification, etc.
The allowances made for royalties payable, both Government
and private.
DeGrussa is an operating mine and capital costs are generally limited to
that required to sustain the operation.
Operating costs are based on current contracts and historical averages.
Exchange rates are based on an average of ANZ bank and CRU
forecasts and vary over the life of the mine. The life-of-mine average rate
is:
oA$ / US$: 0.71.
DeGrussa is subject to Government Royalties and Royalties for Native
Title. Rates for Government Royalties are:
oCopper is 5.0% of net revenue;
oGold is 2.5% of net revenue; and
oSilver is 2.5% of net revenue.
The Royality rate for Native Title is:
o0.5% of gross revenue (copper, gold, silver).
Royalty costs are accounted for under the revenue factors.
Revenue
factors
The derivation of, or assumptions made regarding revenue
factors including head grade, metal or commodity price(s)
exchange rates, transportation and treatment charges, penalties,
net smelter returns, etc.
The derivation of assumptions made of metal or commodity
price(s), for the principal metals, minerals and co-products.
Commodity prices are based on an average of ANZ bank and CRU
forecasts and vary over the life of the mine. The life-of-mine average
values are:
Copper (US$/t) : 5,545;
Gold (US$/oz) : 1,234; and
Silver (US$/oz) : 16.51.
A revenue reduction factor of 23.1% has been applied which includes all
future estimated and calculated transport, smelting, refining and royalty
payments.

SANDFIRE RESOURCES NL

Page 25

Criteria JORC Code Explanation Commentary
Market
assessment
The demand, supply and stock situation for the particular
commodity, consumption trends and factors likely to affect
supply and demand into the future.
A customer and competitor analysis along with the identification
of likely market windows for the product.
Price and volume forecasts and the basis for these forecasts.
For industrial minerals the customer specification, testing and
acceptance requirements prior to a supply contract.

Sandfire is a low cost copper concentrate producer selling into global
market for custom concentrates

Pricing is fundamentally on value of contained metals the main metal
being copper with gold and small silver credits

The price of copper being set based on the LME which is a mature, well
established and publically traded exchange

Sandfire produces a clean concentrate, low in deleterious elements

Sandfire relies upon independent expert publications (CRU, Wood Mac,
Metal Bulletin) and other sources (bank reports, trader reports,
conferences, other trade publications) in forming a view about future
demand and supply and the likely effects of this on both metal prices
and concentrate prices

Sandfire concentrate is sold by competitive tender. The 2015
benchmark TC/RC is well above the break even TC/RC for most
smelters which should underpin robust demand for clean concentrates
for the foreseeable future.
Economic The inputs to the economic analysis to produce the net present
value (NPV) in the study, the source and confidence of these
economic inputs including estimated inflation, discount rate, etc.
NPV ranges and sensitivity to variations in the significant
assumptions and inputs.
DeGrussa is an operating mine with a focus on operating cash margins.
The mine plan created to derive the underground Ore Reserves provides
positive cash margins in all years when all modifying factors are applied.
Social The status of agreements with key stakeholders and matters
leading to social licence to operate.
DeGrussa is an operating mine and all agreements are in place and are
current with all key stakeholders including traditional owner claiments.
Other To the extent relevant, the impact of the following on the project
and/or on the estimation and classification of the Ore Reserves:
Any identified material naturally occurring risks.
The status of material legal agreements and marketing
arrangements.
The status of governmental agreements and approvals critical to
the viability of the project, such as mineral tenement status, and
government and statutory approvals. There must be reasonable
grounds to expect that all necessary Government approvals will
be received within the timeframes anticipated in the Pre-
Feasibility or Feasibility study. Highlight and discuss the
materiality of any unresolved matter that is dependent on a third
party on which extraction of the reserve is contingent.
Sandfire has advised that DeGrussa is currently compliant with all legal
and regulatory requirements.

SANDFIRE RESOURCES NL

Page 26

Criteria JORC Code Explanation Commentary
Classification The basis for the classification of the Ore Reserves into varying
confidence categories.
Whether the result appropriately reflects the Competent Person’s
view of the deposit.
The proportion of Probable Ore Reserves that have been derived
from Measured Mineral Resources (if any).
Underground Ore Reserves have been derived from a mine plan that is
based on extracting the 31 December 2015 Mineral Resources. Proven
Ore Reserves have been derived from Measured Mineral Resources and
Probable Ore Reserves have been derived from both Measured and
Indicated Mineral Resources after consideration of all modifying factors.
Part of C4 and all of C5 Measured Mineral Resources have been
converted to Probable Ore Reserves on the basis that no ore mining
(development or stoping) has been completed as at 31 December 2015.
Experience to date has shown grade and geometry variation at a local
scale therefore the highest level of confidence can only be applied once
an area has been fully developed and detailed stope design completed.
The Ore Reserve classification appropriately reflects the competent
person’s view of the deposit.
Approximately 66% of the Underground Probable Ore Reserve has been
derived from Measured Mineral Resources.
Audits or
reviews
The results of any audits or reviews of Ore Reserve estimates. The Ore Reserve has been peer reviewed internally.
The Ore Reserve estimate is in line with current industry standards.
Discussion of
relative
accuracy/
confidence
Where appropriate a statement of the relative accuracy and
confidence level in the Ore Reserve estimate using an approach or
procedure deemed appropriate by the Competent Person. For
example, the application of statistical or geostatistical procedures to
quantify the relative accuracy of the reserve within stated
confidence limits, or, if such an approach is not deemed
appropriate, a qualitative discussion of the factors which could affect
the relative accuracy and confidence of the estimate.
The statement should specify whether it relates to global or local
estimates, and, if local, state the relevant tonnages, which should
be relevant to technical and economic evaluation. Documentation
should include assumptions made and the procedures used.
Accuracy and confidence discussions should extend to specific
discussions of any applied Modifying Factors that may have a
material impact on Ore Reserve viability, or for which there are
remaining areas of uncertainty at the current study stage.
It is recognised that this may not be possible or appropriate in all
circumstances. These statements of relative accuracy and
confidence of the estimate should be compared with production
data, where available.
Global Underground Ore Reserves for C1 and DG have a higher
confidence level than those stated for C4 and C5 because C1 and DG
modifying factors are based on actual mining and reconciliation data.
One stope has been mined in C4 and none in C5 therefore modifying
factors have a lower confidence level. This lower confidence level is
reflected in the classification of C4 and C5 Ore Reserves as Probable.
See discussion on Classification.
Underground Ore Reserves are split 11 % DG, 37 % C1, 27 % C4, 23 %
C5 with the remaining in stockpiles. Primary ore production is currently
from C1 and DG with production ramp up in progress in C4. C5 will
come on line during the middle of 2016.
Approximately 59 % of the UG Ore Reserves are classified as Proven
with the remaining 41 % classified as Probable.

SANDFIRE RESOURCES NL

Page 27

Competent Person’s Statement – Mineral Resources

The information in this report that relates to Mineral Resources is based on information compiled by Mr. Ekow Taylor who is a Member of The Australasian Institute of Mining and Metallurgy. Mr. Taylor is a permanent employee of Sandfire Resources NL and has sufficient experience that is relevant to the style of mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as Competent Person as defined in the 2012 Edition of the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves. Mr Taylor consents to the inclusion in the report of the matters based on his information in the form and context in which it appears.

Competent Person’s Statement – Ore Reserves

The information in this report that relates to Ore Reserves is based on information compiled by Mr Neil Hastings who is a Member of The Australasian Institute of Mining and Metallurgy. Mr Hastings is a permanent employee of Sandfire Resources NL and has sufficient experience that is relevant to the style of mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as Competent Person as defined in the 2012 Edition of the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves. Mr Hastings consents to the inclusion in the report of the matters based on his information in the form and context in which it appears.

Forward-Looking Statements

Certain statements made during or in connection with this statement contain or comprise certain forward-looking statements regarding Sandfire’s Mineral Resources and Reserves, exploration operations, project development operations, production rates, life of mine, projected cash flow, capital expenditure, operating costs and other economic performance and financial condition as well as general market outlook. Although Sandfire believes that the expectations reflected in such forward-looking statements are reasonable, such expectations are only predictions and are subject to inherent risks and uncertainties which could cause actual values, results, performance or achievements to differ materially from those expressed, implied or projected in any forward looking statements and no assurance can be given that such expectations will prove to have been correct. Accordingly, results could differ materially from those set out in the forward-looking statements as a result of, among other factors, changes in economic and market conditions, delays or changes in project development, success of business and operating initiatives, changes in the regulatory environment and other government actions, fluctuations in metals prices and exchange rates and business and operational risk management. Except for statutory liability which cannot be excluded, each of Sandfire, its officers, employees and advisors expressly disclaim any responsibility for the accuracy or completeness of the material contained in this statement and excludes all liability whatsoever (including in negligence) for any loss or damage which may be suffered by any person as a consequence of any information in this statement or any error or omission. Sandfire undertakes no obligation to update publicly or release any revisions to these forward-looking statements to reflect events or circumstances after today's date or to reflect the occurrence of unanticipated events other than required by the Corporations Act and ASX Listing Rules. Accordingly you should not place undue reliance on any forward looking statement.

SANDFIRE RESOURCES NL

Page 28