11

REGIS RESOURCES LTD

==> picture [128 x 108] intentionally omitted <==

ANNUAL GENERAL MEETING 12 NOVEMBER 2015

2 2

DISCLAIMER & COMPETENT PERSONS STATEMENT

This presentation contains only a brief overview of Regis Resources Limited and its associated entities (“Regis or RRL") and their respective activities and operations. The contents of this presentation, including matters relating to the geology of Regis’ projects, may rely on various assumptions and subjective interpretations which it is not possible to detail in this presentation and which have not been subject to any independent verification.

This presentation contains a number of forward-looking statements. Known and unknown risks and uncertainties, and factors outside of Regis’ control, may cause the actual results, performance and achievements of Regis to differ materially from those expressed or implied in this presentation. To the maximum extent permitted by law, Regis does not warrant the accuracy, currency or completeness of the information in this presentation, nor the future performance of Regis, and will not be responsible for any loss or damage arising from the use of the information. The information contained in this presentation is not a substitute for detailed investigation or analysis of any particular issue. Current and potential investors and shareholders should seek independent advice before making any investment decision in regard to Regis or its activities.

The information in this presentation that relates to Exploration Results is extracted from the ASX announcement released 14 October 2015 entitled “Significant Exploration Drilling Results at Duketon ” and for which Competent Person’s consents were obtained. The Competent Person’s consents remain in place for subsequent releases by the Company of the same information in the same form and context, until the consent is withdrawn or replaced by a subsequent report and accompanying consent.

The information in this presentation that relates to Mineral Resources or Ore Reserves is extracted from the Mineral Resource and Ore Reserve Statement released to the Australian Securities Exchange (ASX) on 16 July 2015 and for which Competent Person’s consents were obtained. The Competent Person’s consents remain in place for subsequent releases by the Company of the same information in the same form and context, until the consent is withdrawn or replaced by a subsequent report and accompanying consent.

The Company confirms that it is not aware of any new information or data that materially affects the information included in the original ASX announcement released on 16 July 2015 and, in the case of estimates or Mineral Resources or Ore Reserves, that all material assumptions and technical parameters underpinning the estimates in the original ASX announcements continue to apply and have not materially changed. The Company confirms that the form and context in which the Competent Person’s findings are presented have not been materially modified from the original ASX announcement.

ASX announcements are available on the Company’s website at www.regisresources.com.au

==> picture [720 x 48] intentionally omitted <==

3 3

ONE YEAR ON

FOCUS AT 2014 AGM

==> picture [332 x 134] intentionally omitted <==

Garden Well February 2014

  • Recovering from flood at GW & RMT

  • Understanding and resolving reconciliation challenges at GW

  • Getting operations to steady state

  • Rebuilding cash position & dividends

  • Rebuilding market confidence

  • Exploration on the backburner

  • Acquisitions not on the agenda

FOCUS AT 2015 AGM

==> picture [332 x 133] intentionally omitted <==

Garden Well November 2015

  • GW reserve updated and performing

  • Operations at steady state and optimisations underway

  • Cash-flow strong, dividend restarted

  • Share price recovery

  • Extensive exploration underway and returning excellent growth potential

  • Two regional acquisitions completed

==> picture [720 x 48] intentionally omitted <==

4 4

REVIEW OF 2015 OPERATIONS

DUKETON OPERATIONS DELIVER STRONG CASHFLOW

==> picture [317 x 364] intentionally omitted <==

----- Start of picture text -----

||||
|---|---|---|
|FY2015|
|Ore mined (Mbcm)|4.65|
|Waste mined (Mbcm)|23.70|
|Stripping ratio (w:o)|5.10|
|Ore mined (Mtonnes)|11.07|
|Ore milled (Mtonnes)|9.84|
|Head grade (g/t)|1.11|
|Recovery (%)|88|
|Gold production (ounces ‘000)|310|
|Cash cost (A$/oz)|826|
|Cash cost inc royalty (A$/oz)|891|
|All in Sustaining Cost (A$/oz)|[1]|994|

----- End of picture text -----

1 AISC calculated on a per ounce of production basis

==> picture [364 x 355] intentionally omitted <==

==> picture [57 x 48] intentionally omitted <==

5 5

CORPORATE

CAPITAL STRUCTURE

SHAREHOLDERS

CAPITAL STRUCTURE
ASX code RRL
Shares on issue 500m
Last price
Market capitalisation
Daily turnover (no. shares)
Unlisted options
FINANCIALS
Cash & bullion (30 Sept 15)
Debt (30 Sept 15)
FY15 EBITDA
FY15 NPAT
FY15 Cash-flow from ops
Dividend
$2.05
A$1,024m
4.1m
13.7m
$98m
$20m
$181M
$87M
$142m
6cps
OPERATIONS SNAPSHOT
Duketon operations (WA)
10Mtpa
McPhillamys project (NSW) 2.2Moz
Resources
7.6Moz
≈290kozpa
resource
Reserves 2.0Moz

==> picture [297 x 121] intentionally omitted <==

----- Start of picture text -----

Australian insto
5%
11% 28% Newmont
9%
North American insto
13%
Directors and mgt
19%
15% UK & Europe insto
Asian insto
Other (retail)
----- End of picture text -----

SHARE PRICE & VOLUME

==> picture [313 x 110] intentionally omitted <==

----- Start of picture text -----

2.5 35
30
2
25
1.5 20
1 15
10
0.5
5
0 0
Share price (A$) Volume (Millions)
----- End of picture text -----

==> picture [720 x 93] intentionally omitted <==

----- Start of picture text -----

Reserves 2.0Moz
----- End of picture text -----

6 6

BALANCE SHEET

NET CASH POSITION BUILDING STRONGLY

==> picture [517 x 239] intentionally omitted <==

----- Start of picture text -----

120
100
80
60
Cash
40
Debt
20
Net cash/(debt)
-
Jun-14 Sep-14 Dec-14 Mar-15 Jun-15 Sep-15
-20
-40
-60
$ Millions
----- End of picture text -----

Strong build in cash-flow since flood affected operations in March 2014 quarter

  • Debt peaked at $61m in the June 2014 quarter

  • Debt now paid down to $20m – due June 2017

  • Cash and bullion $98m (Sept 2015)

Net cash has increased by $125m over last 15 months

==> picture [720 x 48] intentionally omitted <==

7 7

PRODUCTION GUIDANCE 2016

GUIDANCE

Production: 275,000 – 305,000 ounces Cost: AISC A$970 – A$1,070/oz Expansion capital: A$15-20 million

GUIDANCE MID-POINT STATISTICS*

==> picture [479 x 242] intentionally omitted <==

----- Start of picture text -----

||||||
|---|---|---|---|---|
|Moolart|Rosemon|Garden|Total|
|Well|t|Well|
|Ore mined (Mtonnes)|2.8|2.2|5.6|10.6|
|Ore milled (Mtonnes)|2.9|2.3|5.0|10.1|
|Head grade (g/t)|0.89|1.23|0.92|0.98|
|Recovery (%)|91|93|88|91|
|Gold production (ounces|
|75|85|130|290|
|‘000)|
|Cash cost (A$/oz)|820|840|900|860|
|Cash cost inc royalty|880|910|970|930|
|(A$/oz)|
|All in Sustaining Cost|950|1,070|1,040|1,020|
|(A$/oz)|

----- End of picture text -----

2016F operating cash-flow ≈ A$150m at mid-point AISC and current (A$1,550/oz) gold price

==> picture [206 x 395] intentionally omitted <==

==> picture [57 x 48] intentionally omitted <==

  • Errors in summation may occur in this table due to rounding

8 8

FY2016 Q1 OPERATING RESULTS

Moolart
Well
Rosemont
Garden
Well
Total
Ore mined (bcm )
364,919
324,866
577,414
1,267,199
Waste mined (bcm)
1,307,763
2,698,439
1,846,448
5,852,650
Stripping ratio (w:o)
3.58
8.31
3.20
4.62
Ore mined (tonnes)
743,521
736,851
1,519,127
2,999,499
Ore milled (tonnes)
712,364
639,300
1,209,319
2,560,983
Head grade (g/t)
0.92
1.35
0.94
1.04
Recovery (%)
89.5
92.2
84.3
88.2
Gold production (ounces)
18,861
25,567
30,988
75,416
Cash cost (A$/oz)
812
721
910
821
Cash cost inc royalty (A$/oz)
879
785
977
888
All in Sustaining Cost (A$/oz)
959
903
1,040
973

==> picture [720 x 48] intentionally omitted <==

9 9

GARDEN WELL KPIs

==> picture [720 x 455] intentionally omitted <==

10 10

AQCUISITIONS FOR GROWTH

==> picture [428 x 402] intentionally omitted <==

----- Start of picture text -----

10km
Moolart Well
Rosemont
Gloster Tenure
Garden Well
Duketon Mining JV Tenure
Regis Tenure
Major Shear Zone
Gold Project
----- End of picture text -----

  • Compliant with 1996 JORC Code and Guidelines (refer ASX announcement 16 July 2015)

MOOLART WELL AREA

  • Mine life 3 years

  • Successful reserve replacement of production in recent years through oxides and satellites

Recent strategic transactions to further bolster this operation:

  • Acquisition of 365koz Resource* Gloster gold deposit for $1.5m + royalty

  • Duketon Gold Exploration Joint Venture:

  • 373km[2] of gold prospective tenure mostly proximal to MW

  • Regis spending $1m over 2 years to earn 75%

==> picture [57 x 48] intentionally omitted <==

11 11

EXPLORATION UPDATE

SIGNIFICANT RESULTS AT DUKETON IN SEPT15Q

  • Completed 45,517m of exploration drilling on >10 projects and prospects

  • Further significant results at a number of projects:

  • Baneygo – 12km south of Rosemont mill

  • High grade results continue, resource estimation in Dec15Q

  • Idaho – 2.2km north of Baneygo

    • Reconnaissance regional drilling – significant results
  • Early indications of potential of >12km Rosemont-Baneygo shear

  • Tooheys Well – 2.5km south of Garden Well mill

    • Very high grade results, drilling continuing to find extent
  • Coopers – 11km south of Moolart Well mill

    • Significant results continue, resource estimation Dec15Q
  • Rosemont south underground

    • Significant results show continuity of gold mineralization

    • Appears high grade shoot plunging north not south as previously thought

  • Commenced 20,000m drill out of Gloster Gold Deposit

  • Executed formal agreements for Duketon Gold JV – fieldwork to commence

==> picture [720 x 48] intentionally omitted <==

12 12

DUKETON NEAR TERM GROWTH

==> picture [427 x 400] intentionally omitted <==

CURRENT MINE LIVES

Project
Mine Life
Garden Well
7 years
Rosemont
6 years
Moolart Well
3 years
Mill tpa
≈ 5 MT
≈ 2 MT
≈ 3 MT

MINE LIFE EXTENSION OPPORTUNITIES

Project Status
Gloster Resource pending, then DFS
Coopers Resource pending
Erlistoun Scheduling
Baneygo Resource pending
Tooheys Well Further drilling
Rosemont U/G Diamond drilling
GW stage 6 Drilling & study
  • Proximity to mill capacity

  • Known gold hosting structuresShallow & poorly testedStrong extension expected

==> picture [720 x 48] intentionally omitted <==

13 13

BANEYGO GOLD PROJECT

EXCITING HIGH GRADE RESULTS POINT TO NEW DUKETON PROJECT

  • 12km south of Rosemont

  • Gold hosted in Quartz Dolerite similar to Rosemont

  • Baneygo 43koz Au Resource 2004 in 4 small deposits

  • Regis drilled on 40m traverses 330 RC holes for 31,100m

  • Highly significant new gold mineralisation defined over 3km strike outside 2004 Resource

  • Diamond drilling completed for geotechnical and metallurgical purposes

  • Resource update Dec 15Q

Historical drilling grey Regis drilling green and red

==> picture [389 x 48] intentionally omitted <==

14 14

BANEYGO DRILL RESULTS

Hole No Hole No Northing (mN)
Easting (mE)
Hole Depth
(m)
From (m)
To (m)
Interval (m)
Gold g/t
RRLBYRC002 6907462
431925
114
50
83
33
8.35
RRLBYRC023 6906712
432197
102
35
42
7
8.96
RRLBYRC024 6906721
432235
168
87
110
23
2.55
RRLBYRC034 6906092
432357
78
28
42
14
6.95
RRLBYRC082 6907458
431914
72
6
41
35
1.46
RRLBYRC084 6907547
431914
108
60
83
23
3.05
RRLBYRC086 6907627
431901
120
68
85
17
3.73
RRLBYRC100 6906639
432240
138
54
69
15
1.97
RRLBYRC107 6907319
432000
114
69
74
5
12.34
RRLBYRC114 6907502
431914
120
53
90
37
8.73
RRLBYRC117 6907430
431961
102
84
86
2
87.49
RRLBYRC128 6906677
432238
117
78
86
8
8.03
RRLBYRC142 6906492
432313
124
95
105
10
6.36
RRLBYRC162 6907668
431897
117
76
95
19
4.31
RRLBYRC166 6907193
431993
42
12
30
18
3.36
RRLBYRC178 6906130
432346
74
29
42
13
10.79
RRLBYRC201 6907495
431882
54
22
36
14
5.46
RRLBYRC220 New 6906318
432277
33
13
21
8
10.69
RRLBYRC229
6906166
432329
53
39
43
4
24.01
RRLBYRC243 Sept 6906651
432279
174
147
157
10
6.11
RRLBYRC278 15Q 6906627
432329
243
208
219
11
16.65
RRLBYRC315 6907523
431916
103
69
87
18
4.73
RRLBYRC319 6907481
431931
123
94
101
7
12.01
RRLBYRC322 6907602
431914
114
82
107
25
3.27

>50gm intersections are tabled

All coordinates are AGD 84. All holes were drilled at -60 ° to 254 °

All Intercepts calculated using a 0.5g/t lower cut, no upper cut, maximum 2m internal dilution. All assays determined on 1m split samples by fire assay

==> picture [55 x 47] intentionally omitted <==

15 15

BANEYGO GOLD PROJECT

Baneygo

A$1,400/oz pit shells based on recent Regis drilling

Baneygo Beacon

Block Model g/t Au

Baneygo South

$1,400/oz pit shells capturing significant drilling outside existing historical Resources in the 3km area tested

Sydney Mint

==> picture [55 x 47] intentionally omitted <==

15

16 16

ROSEMONT TO BANEYGO

REGIONAL SCALE OPPORTUNITY

==> picture [713 x 433] intentionally omitted <==

----- Start of picture text -----

REGIONAL SCALE OPPORTUNITY
Rosemont

Rosemont-Baneygo trend 20km, significant
intercepts but poorly tested.
 Quartz dolerite host rock at Rosemont
continues to Baneygo and further south
22m @ 2.6g/t, f 22m  Recent RC drilling around Baneygo.
10km
Garden
King John  New discovery Idaho
Well
3m @ 7.7g/t, f 41m  RRLIHRC002 5m @ 3.22g/t Au from 24m
4m @ 8.5g/t, f 28m
 RRLIHRC004 6m @ 3.16g/t Au from 46m
 RRLIHRC008 22m @1.82g/t Au from 28m
10m @ 1.8g/t, f 22m including 6m @ 5.16g/t Au from 44m
8m @ 1.9g/t, f 14m

20km corridor requires further drilling
13m @ 4.9g/t, f 17m Idaho

Previous drilling max 100m deep with
33m @ 8.4g/t, f 50m most only 50m deep
11m @ 7.3g/t, f 21m

21m @ 9.3g/t, f 16m Erlistoun Up to 800m gaps between drill lines
 Continue to test strike continuation north to
Baneygo
Rosemont on 400m traverses
22m @ 2.5g/t, f 26m
5m @ 4.6g/t, f 7m
2m @ 12.6g/t, f 13m
----- End of picture text -----

17 17

IDAHO GOLD PROSPECT

New Gold discovery Idaho 2km north of Baneygo

Idaho Gold Prospect

Baneygo Gold Deposit

North

Block Model g/t Au

==> picture [87 x 97] intentionally omitted <==

==> picture [98 x 45] intentionally omitted <==

==> picture [55 x 47] intentionally omitted <==

17

18 18

ROSEMONT DEEPS

==> picture [720 x 261] intentionally omitted <==

----- Start of picture text -----

South North
500mRL
300mRL
100mRL
High Grade Southern shoot where 6 hole DD
programme was completed originally thought High Grade Central shoot under
to be plunging south. New interpretation has Rosemont Main pit plunging north
shoot plunging north
----- End of picture text -----

  • Further drilling to be designed in Dec15Q to test southern and central high grade shoots

==> picture [720 x 48] intentionally omitted <==

19 19

McPHILLAMYS (NSW)

FOCUS ON KEY INFRASTRUCTURE BEFORE MOVE TO PFS

==> picture [367 x 348] intentionally omitted <==

  • 250km west of Sydney

  • Gold resource 2.2Moz  100% Regis owned

  • Conceptual studies show viable project

  • Current focus on key infrastructure

  • Will then move to PFS  Well established gold mining district • Cadia +40Moz Newcrest • Cowal +3Moz Evolution • Northparkes +2Moz* China Moly

  • Intrinsic portfolio value • Large undeveloped gold resource in Australia – rare and getting rarer!

  • • Low stripping ratio and geological continuity at depth give the in pit resource significant leverage to gold price upside

  • • Medium term development proposition

==> picture [57 x 48] intentionally omitted <==

  • Recent quoted resources from public information

20 20

RECAP

  • Duketon operations steady state and optimising

  • Strong cash-flow underpinning dividends and growth

  • Minimal capital reinvestment required at the Duketon operations

  • Continued exciting exploration results at Duketon

  • Including Baneygo, Idaho, Tooheys Well & Coopers

  • Pointing to extensions of mine life at all three operations

  • Advantage of processing capacity – “ex-capex” developments

  • Bolt on acquisitions to leverage off processing capacity

  • Work continuing to secure infrastructure required for McPhillamys project

Regis business is robust, generating strong free cash-flow with growth opportunities both organic and external

==> picture [720 x 48] intentionally omitted <==

21 21

JORC COMPLIANT MINERAL RESOURCES 31 MARCH 2015

Group Mineral Resources

Group Mineral Resources Group Mineral Resources Group Mineral Resources Group Mineral Resources Group Mineral Resources Group Mineral Resources Group Mineral Resources Group Mineral Resources Group Mineral Resources Group Mineral Resources Group Mineral Resources Group Mineral Resources
as at 31 March 2015
Gold Measured Indicated Inferred Total Resource Competent
Person4
Project Type Cut-Off
(g/t)
Tonnes
(Mt)
Gold Grade
(g/t)
Gold Metal
(koz)
Tonnes
(Mt)
Gold Grade
(g/t)
Gold Metal
(koz)
Tonnes
(Mt)
Gold Grade
(g/t)
Gold Metal
(koz)
Tonnes
(Mt)
Gold Grade
(g/t)
Gold Metal
(koz)
Moolart Well1 Open-Pit 0.4 3.0 0.89 87 29.2 0.75 706 15.0 0.62 300 47.3 0.72 1,093 A
Garden Well1 Open-Pit 0.4 2.7 0.63 54 73.8 0.90 2,131 10.2 0.88 288 86.7 0.89 2,473 B
Rosemont1 Open-Pit 0.4 5.4 1.31 228 20.1 1.27 824 2.8 1.78 160 28.3 1.33 1,212 B
Duketon Main Deposits Sub Total 11.1 1.03 369 123.2 0.92 3,661 28.0 0.83 748 162.3 0.92 4,777
Erlistoun Open-Pit 0.4 - - - 5.7 1.34 247 1.1 1.00 37 6.9 1.28 284 A
Dogbolter Open-Pit 0.4 - - - 2.8 1.11 102 0.4 1.02 13 3.2 1.10 115 A
Petra Open-Pit 0.4 - - - 1.2 1.08 42 0.1 1.09 2 1.3 1.08 44 A
Anchor Open-Pit 0.4 - - - 0.2 1.75 9 0.1 0.95 2 0.2 1.53 11 A
King John3 Open-Pit 1.0 - - - - - - 0.7 3.19 72 0.7 3.20 72 C
Russells Find3 Open-Pit 1.0 - - - - - - 0.4 3.86 55 0.4 4.28 55 C
Baneygo3 Open-Pit 0.5 - - - - - - 0.8 1.67 43 0.8 1.67 43 C
Reichelts Find3 Open-Pit 1.0 - - - 0.1 3.69 17 - - - 0.1 3.69 17 C
Duketon Satellite Deposits Sub Total - - - 10.1 1.28 416 3.6 1.96 223 13.6 1.46 640
Duketon Total 11.1 1.03 369 133.2 0.95 4,077 31.5 0.96 971 175.9 0.96 5,417
McPhillamys Total 0.4 - - - 69.2 0.94 2,087 3.9 0.98 123 73.2 0.94 2,210 B
Regis Grand Total 11.1 1.03 369 202.5 0.95 6,164 35.5 0.96 1,094 249.1 0.95 7,627

Notes

The above data has been rounded to the nearest 100,000 tonnes, 0.01 g/t gold grade and 1,000 ounces. Errors of summation may occur due to rounding.

All Mineral Resources are reported inclusive of Ore Reserves to JORC Code 2012 unless otherwise noted

  1. Mineral Resources and Ore Reserves are reported inclusive of ROM Stockpiles at cut-off grade of 0.4 g/t

  2. Reported under JORC Code 2004

  3. Refer to Group Competent Person Notes

==> picture [720 x 48] intentionally omitted <==

22 22

JORC COMPLIANT ORE RESERVES 31 MARCH 2015

Group Ore Reserves

Group Ore Reserves Group Ore Reserves Group Ore Reserves Group Ore Reserves Group Ore Reserves Group Ore Reserves Group Ore Reserves Group Ore Reserves Group Ore Reserves
as at 31 March 2015
Gold Proved Probable Total Ore Reserve Competent
Person3
Project Type Cut-Off
(g/t)2
Tonnes
(Mt)
Gold Grade
(g/t)
Gold Metal
(koz)
Tonnes
(Mt)
Gold Grade
(g/t)
Gold Metal
(koz)
Tonnes
(Mt)
Gold Grade
(g/t)
Gold Metal
(koz)
Moolart Well1 Open-Pit > 0.4 2.7 0.93 79 3.9 0.92 115 6.5 0.92 194 D
Garden Well1 Open-Pit > 0.4 2.7 0.63 54 31.9 0.93 955 34.5 0.91 1,009 D
Rosemont1 Open-Pit > 0.4 4.4 1.34 188 8.9 1.36 387 13.2 1.35 574 D
Duketon Main Deposits Sub Total 9.7 1.03 321 44.6 1.02 1,456 54.3 1.02 1,777
Erlistoun Open-Pit > 0.5 - - - 3.8 1.48 181 3.8 1.48 181 D
Dogbolter Open-Pit > 0.5 - - - 0.3 1.57 16 0.3 1.57 16 D
Petra Open-Pit > 0.5 - - - 0.6 1.26 25 0.6 1.26 25 D
Anchor Open-Pit > 0.5 - - - 0.1 2.07 6 0.1 2.07 6 D
Duketon Satellite Deposits Sub Total - - - 4.8 1.47 229 4.8 1.47 229
Regis Grand Total 9.7 1.03 321 49.4 1.06 1,685 59.1 1.06 2,006

Notes

The above data has been rounded to the nearest 100,000 tonnes, 0.01 g/t gold grade and 1,000 ounces. Errors of summation may occur due to rounding.

  1. Mineral Resources and Ore Reserves are reported inclusive of ROM Stockpiles at cut-off grade of 0.4 g/t

  2. Cutoff grades vary according to oxidation and lithology domains. Refer to Group Ore Reserves Lower Cut Notes

  3. Refer to Group Competent Person Notes

==> picture [720 x 48] intentionally omitted <==