Ramelius Resources Limited

ACN 001 717 540
140 Greenhill Road. Unley SA 5061 GPO Box 1373, Adelaide SA 5001 DX 52003, Unlev Telephone (08) 8373 6473 / (08) 8373 5588 Facsimile (08) 8373 5917
ASX RELEASE
For Immediate Release 18 November 2005
General Manager The Company Announcements Office Australian Stock Exchange Limited PO Box H224 Australia Square Sydney NSW 1215
Dear Sir/Madam,
RAMELIUS TO MINE WATTLE DAM RESOURCE
The Directors of Ramelius Resources Limited (ASX code:"RMS") are pleased to announce that the Company has today committed to mining its Wattle Dam 7800N resource.
HIGHLIGHTS
- Financial Evaluation of various optimisation models indicates a potential operating profit between \$2.4M and \$3.6M.
- Potential for significant grade overcall.
- Potential for incremental increases in the size and grade of the resource.
- Mine Manager Appointed.
- Statutory Approvals applied for.
- Contract negotiations commenced.
OUTLOOK
- Mining is expected to commence in January 2006, subject to the granting of Statutory Approvals and concluding contracts,
- Results of Geotechnical diamond drilling are expected by December 2005.
- Results of deep RC drilling expected are by December 2005. $\bullet$
ANNOUNCEMENT SUMMARY
Wattle Dam Gold Project
The Wattle Dam Gold Project, located 25kms west of Kambalda in the eastern goldfields of WA, is part of the Company's "Spargoville Regional Project Area".
Spargoville is a highly prospective but under explored belt near Coolgardie, where the Company has a major tenement holding of approximately 280 square kilometres of ground along more than 30 kilometres of strike length, on trend with recent discoveries of gold and nickel.
The Company has now committed to mining the 7800N resource and its development is expected to generate cash flows to fund further exploration throughout the belt for gold, nickel and base metals.
Wattle Dam 7800n Development Studies
Metallurgical test work:
- Indicates Free Milling Ores;
- High Metallurgical Recoveries and
- Low Reagent Usage.
Indicative operating costs:
- Open Cut Mining;
- High Grades from Surface;
- Low Risk Operation.
- Toll Treatment of Ore:
- Mainly Free Digging:
- Robust Return Expected.
Optimisation summary
Using 60km Ore Haulage, \$26/tonne Ore Milling, 96% Mill recovery
| GOLD | MINING RESERVES | OUNCES | CASH COST | OPERATING | OPERATING | TOTAL | STRIPPING | |
|---|---|---|---|---|---|---|---|---|
| PRICE | TONNAGE | GRADE | RECOVERED | per OUNCE | PROFIT | PROFIT @ \$600/oz |
VOLUME | RATIO |
| $(\sqrt{5}/2)$ | (t) | (g/t) | (oz) | (\$) | (\$) | (3) | (BCM) | (BCM:BCM) |
| 560 | 66.139 | 5.88 | 12.012 | 337 | 2.680.554 | 3.161.035 | 478.947 | 17.0 |
| 600 | 69.979 | 5.69 | 12.289 | 344 | 3,143,922 | 3.143.922 | 488.764 | 16.3 |
| 640 | 73.210 | 5.57 | 12.597 | 353 | 3.612.842 | 3.108.976 | 514,576 | 16.5 |
Wattle Dam Project Location

Wattle Dam Ore body

For further information please contact:
Mr. Joe Houldsworth Managing Director Ramelius Resources Limited Ph. 08 9250 6644