Skip to main content

AI assistant

Sign in to chat with this filing

The assistant answers questions, extracts KPIs, and summarises risk factors directly from the filing text.

PERSEUS MINING LIMITED Capital/Financing Update 2020

Mar 29, 2020

46513_rns_2020-03-29_4f71076b-0439-4a41-9a4a-9a496ee05459.pdf

Capital/Financing Update

Open in viewer

Opens in your device viewer

30 March 2020

==> picture [195 x 60] intentionally omitted <==

NEWS RELEASE

PERSEUS MINING UPDATES EDIKAN’S LIFE OF MINE PLAN

Perseus Mining Limited (ASX/TSX: PRU) is pleased to announce details of its updated Life of Mine Plan (“LOMP”) for its Edikan Gold Mine in Ghana, West Africa.

EXECUTIVE SUMMARY

  • The LOMP covers the period from 1 July 2020 and is based on the Company’s revised mining strategy that was implemented in January 2019 involving use of a single mining contractor, mining at a reduced rate of total material movement. Costs, recoveries, mill throughput rates and run times have been updated to reflect recent performance.

  • The LOMP is based on the revised Ore Reserves reported on 20 February 2020 which included Proved and Probable Ore Reserves as at 31 December 2019 of 45.7 million tonnes of ore, grading 1.10 g/t gold and containing 1,608 kozs of gold.

  • Ore loss and dilution included in the estimate of Ore Reserves is based on recent mine to mill reconciliation results. Comparisons of ore tonnes and grade by Edikan’s Mineral Resource models relative to ore tonnes and grade delineated by grade control, indicate that the Mineral Resource estimates on which the Ore Reserves are based are reliable predictors of ore tonnes and grades.

  • The Esuajah South Underground mine has been included in the LOMP, employing a sub-level stoping under rock fill (“SURF”) mining method. Development capital of US$31 million has been assumed.

  • Gold production averages 212,000 ounces/annum over Edikan’s currently estimated mine life of 6.2 years from 1 July 2020, including gold production of approximately 231,000 ounces/annum on average over the next 4 years. The altered production profile relative to the previous LOMP is largely due to the addition of Esuajah South Underground and a significantly larger AG Open Pit.

  • Total estimated gold production of 1,307,000 ounces over the life of mine is 95% higher than the amount estimated for the corresponding period in the previous LOMP. The substantial increase is largely due to the addition of Esuajah South Underground and a much larger AG Open Pit.

  • Forecast weighted average all-in site costs, including all direct production costs, royalties, waste stripping costs and sustaining capital expenditure (“AISC”), are in the range of US$870-US$890 per ounce over the remaining life of mine. This represents a 5% decrease in average AISC relative to the previous LOMP, over the corresponding period. Forecast sustaining capital costs (including the cost of site rehabilitation) of US$37 million or US$28 per ounce are included in the AISC estimate.

  • Edikan’s revised LOMP forecasts strong positive after-tax cash flows totalling approximately US$356 million (or A$0.51per share at an A$:US$ exchange rate of 0.60), assuming a flat spot gold price of US$1,300 per ounce for the remaining mine life.

  • The revised LOMP should be read in conjunction with, and added to, previously published production and cost guidance for the Half Year ending 30 June 2020.

Perseus Mining Limited ABN 27 106 808 986 Level 2, 437 Roberts Road Subiaco WA 6008 PO Box 1578 Subiaco WA 6008 Telephone: +61 8 6144 1700 Facsimile: +61 8 6144 1799 Email: [email protected] Website: www.perseusmining.com

==> picture [120 x 37] intentionally omitted <==

UPDATED LIFE OF MINE PLAN FOR EDIKAN GOLD MINE

1. Overview

The updated LOMP for Edikan involves mining and processing of ore from three open pits and one underground mine (Refer to Figure 1 below) based on optimisation, design and scheduling using a gold price of US$1,300 per ounce and input parameters based on Perseus’s operating experience including costs from recently executed supply contracts.

Figure 1: Edikan Gold Mine layout

==> picture [513 x 335] intentionally omitted <==

Based on the LOMP, the key forecast operating statistics for Edikan are summarised below in Table 1 below .

Table 1: Overview Key Parameters of the updated LOMP

Parameter Units Average peryear Total
Ex-Pit Mining **FY21-241 ** Life of Mine
Total ore + waste mined Mt 26.8 114.9
Waste mined Mt 19.6 81.1
Ore mined Mt 7.2 33.82
Head grade g/t gold 1.18 1.20
Stripratio t:t 2.7 2.4

Note: 1. Perseus has a financial year that ends on 30 June.

  1. The LOMP includes all Ore Reserves that are expected to remain as at 30[th] June 2020.

2 | P a g e

==> picture [120 x 37] intentionally omitted <==

Table 1: Overview Key Parameters of the updated LOMP (Continued)

Parameter Units Average peryear
Total
Processing **FY21-241 ** Life of Mine
Quantity ore processed Mt 7.2
1.15
264
87.8
231
42.32
1.09
1,483
88.2
1,307
Head grade processed g/t gold
Contained gold ‘000 ounces
Gold recovery rate %
Gold production ‘000 ounces
Operating and Capital Costs
Average mining costs US$/tonne mined 4.38
8.41
2.53
844
88
19
951
31
4.62
8.67
2.45
763
88
28
879
31
Average processing costs US$/tonne processed
Average general & administration (“G&A) costs US$/tonne processed
Production costs US$/ounce
Royalty US$/ounce
Sustaining capital US$/ounce
All-in site costs US$/ounce
Development Capital US$ Million

Note: 1. Perseus has a financial year that ends on 30 June. 2. Includes Ore mined ex-pit plus Ore drawn from ROM stockpile and Heap Leach pads. 3. The LOM Plan is based on expected June 2020 face positions.

2. Comparison of Key Parameters relative to the August 2018 Edikan LOMP

The current LOMP differs relative to the prior version of the LOMP released in August 2018, as shown below in Table 2 .

Table 2: Overview Key Parameters of the updated LOMP

Parameter Units **2018 LOMP1 ** **2020 LOMP2 ** **% Change **
Mining
Total ore + waste mined Mt 62.9 114.9 +83
Waste mined Mt 44.6 81.1 +82
Ore mined Mt 18.3 33.8 +85
Head grade g/t gold 1.06 1.20 +13
Strip ratio t:t 2.4 2.4 -
Processing
Average quantity ore processed Mt/year 6.4 6.9 +8
Head grade processed g/t gold 0.94 1.09 +16
Contained gold ‘000 ounces 764 1,483 +94
Gold recovery rate % 87.7 88.2 +1
Gold production ‘000 ounces 670 1,307 +95
Average gold production ‘000 ounces/ year 168 212 +26
Operating and Capital Costs
Average mining costs US$/tonne mined 3.86 4.62 +20
Average processing costs US$/tonne processed 9.63 8.67 -10
Average Site G&A costs US$/tonne processed 2.34 2.45 +5
Production costs US$/ounce 813 763 -6
Royalty US$/ounce 88 88 -
Sustaining capital US$/ounce 23 28 +22
All-in site costs US$/ounce 924 879 -5

Notes: 1. FY2019 and FY2020 omitted from 2018 LOMP and gold price changed to $1,300/oz for comparison purposes 2. LOMP commences 1 July 2020 and ends 31 August 2026. 3. The LOM Plan is based on expected June 2020 face positions.

3 | P a g e

==> picture [120 x 37] intentionally omitted <==

Mineral Resources and Ore Reserves

The 31 December 2019 global Measured and Indicated Mineral Resource for Edikan forms the basis of the LOMP. It was estimated as 83.3 million tonnes grading at 1.01 g/t gold, containing 2,699 koz of gold as shown in Table 3.

A further 7.3 Mt of material grading at 1.48 g/t gold and containing a further 348 koz of gold are classified as Inferred Resources. Details of these estimates are shown below in Table 4 .

Readers are referred to ASX release “Perseus Mining Updates Edikan Gold Mine’s Mineral Resource & Ore Reserves” dated 20 February 2020 and the notes contained therein. The Company confirms that it is not aware of any information that would result in a material change to the estimates of Mineral Resources previously released.

Table 3: Edikan Measured and Indicated Mineral Resources – 31 December 2019[9, 10, 11]

Project Type Measured Resources Indicated Resources M & I Resources
Quantity
Grade
Gold
Quantity
Grade
Gold
Quantity
Grade
Gold
Mt
g/t
gold
‘000
oz
Mt
g/t
gold
‘000
oz
Mt
g/t
gold
‘000
oz
AF Gap1, 2, 3
Esuajah North2, 3, 4
Fetish1, 2, 3, 5
Bokitsi South2, 3, 6
Open Pit
Open Pit
Open Pit
Open Pit
10.2
1.00
326
3.3
0.80
85
7.7
1.00
248
1.3
1.81
73
21.8
0.92
645
4.8
0.74
114
14.1
0.92
418
1.6
1.30
65
32.0
0.94
971
8.1
0.77
199
21.8
0.95
666
2.8
1.53
139
Sub-Total 22.5
1.01
732
42.2
0.91
1,242
64.7
0.95
1,975
Esuajah South7
Heap Leach2, 8
Stockpiles
U/ground
Stockpile
Stockpile
0.0
0.0
0
-
-
-
5.9
0.63
119
9.0
1.8
530
3.6
0.6
75
-
-
-
9.0
1.8
530
3.6
0.6
75
5.9
0.63
119
Total 28.4
0.93
852
54.8
1.05
1,848
83.3
1.01
2,699

Notes:

  1. Based on January 2017 Mineral Resource models constrained to US$1,800/oz pit shells.

  2. Depleted to 31 December 2019 mining surfaces. 3. 0.4g/t gold cut-off applied. 4. Based on June 2019 Mineral Resource model constrained to US$1,800/oz pit shell.

  3. Includes Bokitsi North lode.

  4. Based on November 2019 Mineral Resource model constrained to US$1,800/oz pit shell.

  5. Based on July 2019 Mineral Resource model, 0.8g/t gold cut-off applied. 8. At zero cut-off grade. 9. All Mineral Resources are current as at 31 December 2019.

  6. Mineral Resources are inclusive of Ore Reserves.

  7. Rounding of numbers to appropriate precisions may have resulted in apparent inconsistencies.

Table 4: Edikan Inferred Mineral Resources – 31 December 2019[7, 8]

Inferred Resources
Deposit Deposit Type Quantity
Grade
Gold
Mt
g/t gold
‘000 oz
AF Gap1, 2, 3
Esuajah North2, 3, 4
Fetish1, 2, 3, 5
Bokitsi South2, 3, 6
Esuajah South7
Open Pit
Open Pit
Open Pit
Open Pit
U/ground
0.3
0.95
10
0.03
0.96
1
0.7
0.95
22
0.3
1.06
9
6
1.6
307
Total 7.3
1.48
348

Notes:

4 | P a g e

==> picture [120 x 37] intentionally omitted <==

  1. Based on January 2017 Mineral Resource models constrained to US$1,800/oz pit shells.

  2. Depleted to 31 December 2019 mining surfaces.

  3. 0.4g/t gold cut-off applied.

  4. Based on June 2019 Mineral Resource model constrained to US$1,800/oz pit shell.

  5. Includes Bokitsi North lode.

  6. Based on November 2019 Mineral Resource model constrained to US$1,800/oz pit shell.

  7. Based on July 2019 Mineral Resource model, 0.8g/t gold cut-off applied.

  8. All Mineral Resources are current as at 31 December 2019.

  9. Rounding of numbers to appropriate precisions may have resulted in apparent inconsistencies.

The updated Edikan Ore Reserve which is summarised below in Table 5 is estimated at 45.7 million tonnes of ore, grading 1.10 g/t gold and containing 1,608 koz of gold and is based on the re-estimated Edikan Mineral Resources as at 31 December 2019. The updated Ore Reserve is based on a gold price of $1,300per ounce (up from $1,200per ounce in the previous LOMP) on an updated pit optimisation, design and schedule on the new Bokitsi South open pit Mineral Resource, updated pit optimisation, design and scheduling of the AFG and Fetish deposits based on reduced operating costs and a new Esuajah South Underground Ore Reserve following an update of the feasibility study for the deposit. Table 5 reports the Ore Reserves by category, deposit and type, above variable cut-off grades. The classification categories of Proved and Probable under the JORC Code are equivalent to the CIM categories of the same name (CIM, 2010).

Readers are referred to ASX release “Perseus Mining Updates Edikan Gold Mine’s Mineral Resource & Ore Reserves” dated 20 February 2020 and the notes contained therein. The Company confirms that it is not aware of any information that would result in a material change to the estimates of Ore Reserves previously released.

[,] Table 5: Edikan Gold Mine Proved and Probable Ore Reserves as at 31 December 2019³[,]

Deposit Deposit
Type
Proved Probable Proved + Probable
Quantity
Grade
Gold
Quantity
Grade
Gold
Quantity
Grade
Gold
Mt
g/t
gold
koz
Mt
g/t
gold
Koz
Mt
g/t
gold
koz
AF Gap¹,⁴
EsuajahNorth¹,⁴
Fetish¹,⁴
Bokitsi South¹,⁴
Open Pit
Open Pit
Open Pit
Open Pit
6.8
1.14
248
0.4
0.91
11
4.4
1.18
165
0.9
2.11
58
11.9
1.05
402
0.6
0.86
17
7.1
1.09
248
0.4
1.70
24
18.6
1.09
650
1.0
0.88
28
11.4
1.13
414
1.3
1.97
82
Sub-total Open Pit 12.3
1.22
482
20.0
1.08
690
32.3
1.13
1.173
Esuajah South
Heap Leach⁵
ROM Stockpiles²
U/ground
Stockpile
Stockpile
5.9
0.63
119
3.8
1.96
241
3.6
0.6
75
3.8
1.96
241
3.6
0.6
75
5.9
0.63
119
Total 18.3
1.02
601
27.4
1.14
1,007
45.7
1.10
1,608

Notes:

  1. Based on December 2019 Mineral Resource estimate which is depleted to 31[st] December 2019.

  2. Based on stockpile balance as at 31[st] December 2019.

  3. All Ore Reserves current as at 31[st] December 2019.

  4. Variable gold grade cut-off based on recovery of each material type in each deposit: Oxide 0.35 – 0.40 g/t, Transition 0.50 – 0.70 g/t and Fresh 0.50 – 0.55 g/t.

  5. Based on 0.40 g/t gold grade cut-off.

  6. Inferred Mineral Resource is considered as waste, t : t.

  7. Rounding of numbers to appropriate precisions may have resulted in apparent inconsistencies.

5 | P a g e

==> picture [120 x 37] intentionally omitted <==

Proven and Probable Ore Reserves are found within the economic limits of four discrete open pits, an underground project and stockpiles that have been designed based on Measured and Indicated Mineral Resources that incorporated all available Resource in-fill drilling results, a gold price of US$1,300per ounce and mining, processing and general and administration parameters generally derived from recent operating experience. Note that the Esuajah North pit is due to be mined out completely before the commencement of the LOMP in July 2020.

3. Gold production profile

With the aim of maximising the return on funds employed at Edikan, the mining sequence of the pits along with mill feed profile has been optimised and scheduled. The result of this scheduling is that the gold production profile and resulting cash flows from Edikan remain strong for the remainder of the mine life. (Refer to Figures 2, 3 and 4 below.)

Figure 2: Edikan Gold Mine - scheduled monthly material movement ex-pit (Mtonnes)

==> picture [489 x 223] intentionally omitted <==

Figure 3: Edikan Gold Mine – yearly tonnes and grade to Mill

==> picture [489 x 235] intentionally omitted <==

6 | P a g e

==> picture [120 x 37] intentionally omitted <==

Figure 4: Edikan Gold Mine – yearly Gold Production by Pit

==> picture [486 x 221] intentionally omitted <==

----- Start of picture text -----

Gold Production
300
250
200
150
100
50
-
FY20-21 FY21-22 FY22-23 FY23-24 FY24-25 FY25-26 FY26-27
BKS_FINAL AFG_FINAL FET_STG2 FET_FINAL ESS_UG ROM Heap Leach
'000 oz
----- End of picture text -----

The Esuajah South deposit is now included in Edikan’s production profile, due to a reduction in processing costs and an increase in the gold price used to determine Ore Reserves.

4. Improved operating efficiencies

In 2016, Perseus invested heavily in upgrading key elements of Edikan’s process plant and also establishing standby power generating capacity to ensure continuity of operations irrespective of the availability of power from the national electricity grid. These works were successful in increasing the run time on the processing plant.

During 2018 and 2019, the focus of business improvement was to increase the processing plant throughput rate. This was achieved through improving blast fragmentation in the open pit and optimising mill load through the use of the MillSlicer and MillStar technology, as well as other initiatives. The combined impact of the initiatives was to lift throughput rate by more than 10%, thereby reducing unit processing and G&A costs significantly. Further initiatives to optimise the processing circuit are in progress, with further cost improvements possible.

Assumed, average, annual processing throughput rate of ore is 7.0Mtpa, with throughput rates variable by material type and deposit as shown in Table 6 . The processing circuit involves single stage crushing, semiautogenous grinding, gravity recovery, flotation, regrind and CIL. Run time, which is the product of availability and utilisation, is forecast to average 92.6% for the remaining life of mine

The process metallurgical recovery for gold is fixed by material type in each deposit. Gold recovery rates range from 56-61% for oxide ore and 70-90% for primary ore. The variable recoveries are a function of differing metallurgical properties of ores from different deposits. Recovery by pit and ore type are as shown in Table 7 .

7 | P a g e

==> picture [120 x 37] intentionally omitted <==

Table 6: Mill throughput by material type and pit

Mill Throughput Rate by Ore Type (tph) Mill Throughput Rate by Ore Type (tph)
Deposit Oxide Transition Fresh
AF Gap
Bokitsi
Fetish
Esuajah North
Heap Leach
156
200
135
154
95
886
1,136
763
786
-
844
1,082
727
776
-

Table 7: Metallurgical recoveries by material type and pit

Recovery by Ore Type (%) Recovery by Ore Type (%)
Deposit Oxide Transition Fresh
AF Gap
Bokitsi
Fetish
Esuajah North
Heap Leach
61.0
56.0
61.0
61.0
67.0
73.4
64.0
73.4
73.4
-
88.0
70.21
90.0
90.0
-

1 Average value for the remaining material, the recovery for Bokitsi is variable based on the input grade

5. Future cash flows and sensitivity analysis

Based on Edikan’s revised LOM gold production and cost parameters, the net after tax cash flows forecast to be generated by the mine from 1 July 2020, at US$1,300 per ounce gold price, are estimated to total US$356 million or A$0.51 per share (assuming an A$:US$ exchange rate of 0.60).

The sensitivity analysis shown below in Table 8 summarises the sensitivity of Edikan’s net after tax cash flows to movements in the gold price.

Table 8: Sensitivity Edikan’s After Tax Cashflow to gold price movements

Gold Price Gold Price
US$1,200/ounce US$1,250/ounce US$1,300/ounce US$1,350/ounce
US$280 million US$318 million US$356 million US$393 million
A$0.40/share A$0.45/share A$0.51/share A$0.56/share

Within an expected short-term gold price trading range of US$1,200 per ounce to US$1,350 per ounce, the projected cash flows of the mine remain robust and capable of materially contributing to the development funding of Perseus’s current project in construction, namely the Yaouré Gold Mine, located in Côte d’Ivoire.

8 | P a g e

==> picture [120 x 37] intentionally omitted <==

This report has been authorised for release by the Board. To discuss any aspect of this announcement, please contact:

Managing Director: Jeff Quartermaine at telephone +61 8 6144 1700 or email [email protected]; Media Relations: Nathan Ryan at telephone +61 4 20 582 887 or email [email protected] (Melbourne)

Caution Regarding Forward Looking Information :

This report contains forward-looking information which is based on the assumptions, estimates, analysis and opinions of management made in light of its experience and its perception of trends, current conditions and expected developments, as well as other factors that management of the Company believes to be relevant and reasonable in the circumstances at the date that such statements are made, but which may prove to be incorrect. Assumptions have been made by the Company regarding, among other things: the price of gold, continuing commercial production at the Edikan Gold Mine and the Sissingué Gold Mine without any major disruption due to the COVID-19 pandemic or otherwise, development of a mine at Yaouré, the receipt of required governmental approvals, the accuracy of capital and operating cost estimates, the ability of the Company to operate in a safe, efficient and effective manner and the ability of the Company to obtain financing as and when required and on reasonable terms. Readers are cautioned that the foregoing list is not exhaustive of all factors and assumptions which may have been used by the Company. Although management believes that the assumptions made by the Company and the expectations represented by such information are reasonable, there can be no assurance that the forward-looking information will prove to be accurate. Forward-looking information involves known and unknown risks, uncertainties, and other factors which may cause the actual results, performance or achievements of the Company to be materially different from any anticipated future results, performance or achievements expressed or implied by such forwardlooking information. Such factors include, among others, the actual market price of gold, the actual results of current exploration, the actual results of future exploration, changes in project parameters as plans continue to be evaluated, as well as those factors disclosed in the Company's publicly filed documents. The Company believes that the assumptions and expectations reflected in the forward-looking information are reasonable. Assumptions have been made regarding, among other things, the Company’s ability to carry on its exploration and development activities, the timely receipt of required approvals, the price of gold, the ability of the Company to operate in a safe, efficient and effective manner and the ability of the Company to obtain financing as and when required and on reasonable terms. Readers should not place undue reliance on forward-looking information. Perseus does not undertake to update any forward-looking information, except in accordance with applicable securities laws.

Competent Person Statement

All production targets for the Edikan Gold Mine referred to in this report are underpinned by estimated Ore Reserves which have been prepared by competent persons in accordance with the requirements of the JORC Code. The information in this report that relates to Mineral Resources and Ore Reserves for the Esuajah North deposit at the Edikan Gold Mine was first reported by the Company in compliance with the JORC Code 2012 and NI43-101 in a market announcement entitled “Perseus Mining Updates Mineral Resources & Ore Reserves” released on 29 August 2019. The information in this report that relates to the Mineral Resources for the Edikan deposits (other than the Fetish, AFG, Bokitsi South, Esuajah North and Esuajah South deposits) was first reported by the Company in compliance with the JORC Code 2012 and NI43-101 in a market announcement released on 29 August 2018. The information in this report that relates to Ore Reserves for the Edikan deposits (other than the Fetish, AFG, Bokitsi South, Esuajah North and Esuajah South deposits) was first reported by the Company in compliance with the JORC Code 2012 and NI43-101 in a market announcement entitled “Perseus Mining Updates Mineral Resources & Ore Reserves” released on 29 August 2018. The above-mentioned deposits have been updated for mining depletion as at 31 December 2019 in a market announcement “Perseus Mining Updates Edikan Gold Mine’s Mineral Resource & Ore Reserves” released on 20 February 2020. The information in this report that relates to the Mineral Resource and Ore Reserve estimates for the Bokitsi South and Esuajah South underground and to the Ore Reserve estimates for the Fetish and AFG deposits at the Edikan Gold Mine was first reported by the Company in compliance with the JORC Code 2012 and NI43-101 in a market announcement “Perseus Mining Updates Edikan Gold Mine’s Mineral Resource & Ore Reserves” released on 20 February 2020. The Company confirms that it is not aware of any new information or data that materially affect the information in those market releases and that all material assumptions underpinning those estimates and the production targets, or the forecast financial information derived therefrom, continue to apply and have not materially changed. The Company further confirms that material assumptions underpinning the estimates of Ore Reserves described in “Technical Report — Central Ashanti Gold Project, Ghana” dated 30 May 2011 continue to apply.

9 | P a g e