ASX Announcement (ASX : OBM)

2 August 2019

Cost of Process Plant Remedial Work Lower Than Forecast

EPCM Cost Estimate 43% Lower at A$8.5M

Highlights:

  • Detailed review of Davyhurst Process Plant and associated plant infrastructure undertaken by GR Engineering Services Ltd (“GRES”)

  • EPCM (+/- 15%) capital cost estimate for remedial work program is A$8.5M

  • EPCM estimate includes contingency of A$0.84 million

  • Re-start capital cost now approximately A$6.5m lower than earlier estimates

  • Lower capital cost seen as a significant benefit, enhancing potential project returns

Ora Banda Mining Limited (ASX:OBM) (“Ora Banda”, “Company”) is pleased to advise that a detailed review of the Company’s Davyhurst Gold Processing Plant and the plant’s associated infrastructure, has now been completed, with a clear positive outcome.

GRES has estimated the capital cost to complete remedial works and recommission this processing plant on an EPCM basis to be A$8.52 million . This represents a 43% reduction in the Company’s previous capital cost estimate* and includes a contingency of A$0.84 million.

Summary tables of major items included in this cost estimate are included on the following page.

Ora Banda also advises that GRES have estimated the time to complete the remedial works program and recommission the Davyhurst processing plant to be only 24 weeks from commencement of the remedial works**.

Ora Banda Managing Director, David Quinlivan, said:

“We are pleased to provide further clarity on the capital cost estimate to complete outstanding remedial works and to recommission the Davyhurst Gold Processing Plant. We are also pleased that our previous estimate of A$15 million* for this remedial work program has proven to be conservative and believe these projected capital cost savings will significantly enhance the overall economics of this project.

* Refer to Prospectus dated 30 April 2019 (P27) and ASX Announcement 7 June 2019

** For clarity the remedial works program is not scheduled to commence until after completion of positive feasibility study

For further information please contact:

David Quinlivan Managing Director +61 418 948 944

==> picture [97 x 45] intentionally omitted <==

==> picture [129 x 39] intentionally omitted <==

Table 1 – GR Engineering Services Ltd Cost Summary by Area

AREA SUMMARY TOTAL($M)
200 Earthworks 0.17
205 General Site Improvements(Painting) 0.47
310 Crushing& Screening 1.46
320 Coarse & Fine Ore Storage & Handling 0.19
330 Grinding& Classification 0.91
332 GravityRecovery& Separation 0.04
340 Leaching& Adsorption 0.49
350 Gold Recovery 0.17
360 Reagent Mixing& Distribution 0.02
370 Power Reticulation 0.56
390 Water Storage & Reticulation 0.06
391 Raw Water Supply 0.54
400 Tails Thickening& Disposal 0.14
420 Air Services Supply& Reticulation 0.01
430 Administration Buildings and Offices 0.23
499 Plant Piping 0.26
500 Engineering 1.34
503 Commissioning 0.28
805 Cranage & Equipment Hire 0.77
830 TemporaryFacilities 0.13
840 Mobilisation / Demobilisation 0.04
998 Flights 0.12
Total 8.52

* Site accommodation, meals and fuel are excluded from the estimate.

Table 2 – GR Engineering Services Ltd Major Components of Capital Estimate

ITEM TOTAL($M)
Earthworks 0.17
Surfaceprotection 0.47
Secondarycrusher surge bin replacement 0.20
Tertiarycrusher surge bin replacement 0.22
Crushingarea replacement magnets 0.31
Crushingarea replacement metal detectors 0.05
Mill 1&2 liner replacements 0.34
Existingbores 0.15
New bores 0.26
Maintenance office 0.23
Total – Major Items 2.40

*All estimates rounded to two decimal places.