Minsud announces results of Phase 2 drilling program at Chita Valley Project, San Juan, Argentina
TORONTO, ONTARIO – Minsud Resources Corp. (TSX-V: MSR) (“Minsud” or the “Company”), is pleased to announce the completion of Phase 2 diamond drilling program, comprised of 12 holes, 5,818 meters, with variable depths between 350-650 meters, completed at the Chita and Chinchillones porphyry targets, part of the Chita Valley Project. Together with Phase 1, the Company completed a total of 9,377 meters during 2020, as shown in Map 1.
The program tested targets identified during the systematic multidisciplinary exploration program conducted in the sector during Phase 1 drilling program completed during first half of 2020, and the results from the pole-dipole geophysical survey covering 68 kilometers over 13 Induced Polarization (IP) lines completed on July 2020.
==> picture [447 x 365] intentionally omitted <==
Map 1: Chinchillones and Chita Polymetallic and Porphyry Complex
1
Target Chinchillones: Scouting drill holes CHDH20-04 and CHDH20-05 (Phase 1) together with drill hole CHDH20-17 (Phase 2) confirm the presence of a deep porphyry system and linked shallow polymetallic Cu-Au-Pb-Zn mineralizations hosted in breccias and veins at the North West edge of the Chita Valley. Early Chalcopyrite-molybdenum veins crosscut by hydrothermal late veins suggests a telescoping hydrothermal event overimpossed to the porphyry system, potassium alteration (Magnetite-Biotite) appears as a relict in the widespread Quartz-sericite alteration. At the southern edge of the Chinchillones area, the porphyry system appears to be intruded by a late phreato magmatic breccia (Diatreme) and a Dacite Dome. Intermediate sulphidation (IS) Pb-Zn-Mn-Au-Ag mineralization types, appear to be related with these magmatic hydrothermal breccias aligned in the North North East direction. Anomalous values of Cu-Au-Ag-Pb-Zn detected in drillhole CHDH20-08 are a typical dome-related mineralization.
The Cu-Mo and Pb-Zn +/- Au Ag mineralization identified at the Chinchillones area confirms that this area constitutes a high priority target with significant potential of exploration.
| Phase 2: Chinchillones area - Summary of Analytical Results | |
|---|---|
| Hl ID | From To Length Au Ag Cu Mo Pb Zn |
| oe | (mt) (mt) (mts) (*) g/t g/t % ppm ppm **ppm ** |
| CHDH20-07 | 66 82 16 0.07 13.63 0.46 81 728 2,276 |
| including | 66 68 2 0.11 25.30 2.68 99 1,950 8,610 |
| 120 186 66 0.11 14.35 0.14 65 1,321 3,061 |
|
| 264 393 129 0.02 9.69 0.05 99 1,047 4,926 |
|
| CHDH20-08 | 42 68 26 0.12 4.80 0.07 2 756 1,629 |
| 114.5 115.3 0.8 0.99 307.00 7.45 7 3,000 18,850 |
|
| 303 309 6 0.34 54.22 0.27 32 498 3,579 |
|
| 354 450 96 0.07 15.16 0.03 3 2,140 5,467 |
|
| CHDH20-09 | 122 128 6 0.19 24.26 0.11 6 737 1,553 |
| 450 456 6 0.07 76.64 0.17 5 1,728 4,973 |
|
| CHDH20-10 | 12 22 10 0.36 75.79 2.66 4 22,489 7,079 |
| including | 16 18.3 2.3 0.60 163.78 8.43 6 49,170 23,052 |
| 65 69 4 0.10 14.40 0.10 47 541 3,763 |
|
| 132 136 4 0.11 10.65 0.03 2 5,493 20,810 |
|
| 235 241 6 0.13 35.87 0.19 2 2,153 16,743 |
|
| CHDH20-17 | 100 178 78 0.16 6.47 0.21 87 144 3,531 |
| 240 347 107 0.20 24.07 0.11 16 2,046 5,942 |
|
| 464 524 60 0.02 1.49 0.24 137 59 740 |
|
| CHDH20-18 | 104 238 134 0.07 3.38 0.19 76 68 190 |
| including | 107 108 1 0.32 102.00 3.52 15 430 2,850 |
| 285 292 7 0.35 5.00 0.28 39 60 167 |
|
| 388 398 10 0.06 11.71 0.25 57 76 408 |
(*) Intervals reported in the above table are not true thicknesses
Target Chita North porphyry (PNO): This target was tested through drill holes CHDH20-11, CHDH20-12, CHDH20-14, CHDH20-15 and CHDH20-16. The main rock type intercepted corresponds to an Andesite porphyry. The dominant hydrothermal alteration corresponds to a marginal propylitic Py halo (3%-5%). Drill hole CHDH20-12, approximately at 412 meters deep, intercepted a porphyry with Potassium alteration type, conformed by Biotite-Magnetite +/- Potassium Feldspar. The mineralization is scarce, associated to North North East structures with Chalcopyrite-Sphalerite (intermediate sulphidation system) and relict of primary Molybdenite mineralization. The continuity to the north of the potassium alteration detected at the southern margin of the Chita Valley is still not clear and should be confirmed through future geological mapping and drillings.
Target Chita South porphyry (PSU): It was only tested through drill hole CHDH20-13. Mineralization of 0.3% to 0.4% Cu, up to 100 - 120 meters. The best grades are associated with Chalcocite (product of a secondary enrichment process) coating on Pyrite and Chalcopyrite, together with copper oxide fillings (mix Cu Ox –Sulphur zone).
2
| Phase 2: Chita PSU and PNO - Summary of Analytical Results | |
|---|---|
| Hl ID | From To Length Au Ag Cu Mo Pb Zn |
| oe | (mt) (mt) (mts) (*) g/t g/t % ppm ppm **ppm ** |
| CHDH20-11 | 424 480 56 0.02 0.64 0.09 271 7 29 |
| CHDH20-12 | 32 48 16 0.08 4.74 0.39 40 155 492 |
| including | 39.5 40 0.5 0.88 64.20 3.47 351 118 780 |
| 332 342 10 0.05 2.76 0.17 35 72 263 |
|
| CHDH20-13 | 24 126 102 0.08 2.06 0.33 253 39 104 |
| 152 192 40 0.04 0.87 0.11 189 18 181 |
|
| CHDH20-14 | 120 124 4 0.06 2.37 0.06 22 96 5,765 |
| 174 182 8 0.08 2.81 0.04 6 610 3,303 |
|
| CHDH20-15 | 288 292 4 0.21 9.30 0.16 5 110 300 |
| CHDH20-16 | Intercepts hydrothermal pyrite halo |
(*) Intervals reported in the above table are not true thicknesses
The results of this Phase 2 scout drilling exploration program confirm very interesting intercepts that support effectively the presence at shallow and at down depth level of a Zn-Pb-Cu-(Ag-Au) polymetallic epithermal system and deeper parental porphyry Cu-Mo-Au open to the North North East at Chinchillones area.
The geological team is currently working on detailed re-logging of the Phase 2 drill core and mapping, together with the review of all the available structural and geochemical data in order to assist on targeting for the next Phase 3 drill program that is being designed and scheduled to commence during the first half of 2021.
Conceptual Geological Model
Different magmatic-hydrothermal breccias observed at Chita and Chinchillones reflect a complex sequence of multiple events that can be linked to explosive events developing in the upper parts of the porphyry system during their emplacement, uplift and unroofing. In fact, at Chita and Chinchillones, a large part of the evolution of this porphyry system would have developed in a tectonic framework characterized by the occurrence of high rates of regional tectonic uplift and erosion, which would have favored the generation of telescoping processes related to mineralization process and the formation of the diatreme complex.
Quality Assurance/Quality Control
All core samples were submitted to the ALS Laboratories in Mendoza, Argentina for preparation and analysis. All samples were analyzed for Au by fire assay/ AA finish 50g, plus a 48-element ultra-trace four acid digest with ICP-MS and ICP-AES finish. Minsud followed industry standard procedures for the work with a quality assurance/quality control (QA/QC) program. Field duplicates, standards and blanks were included with all sample shipments to the principal laboratory. Minsud detected no significant QA/QC issues during review of the data.
Mr. Mario Alfaro, Professional Geoscientist, VP-Exploration of the Company, is a qualified person as defined by Canadian National Instrument 43-101. Mr. Alfaro visited the property and has read and approved the contents of this release.
About the Chita Valley Project, San Juan Province:
The Chita Valley Project is a large exploration stage porphyry system with classic alteration features, widespread porphyry style Cu-Mo-Ag-Au mineralization and associated gold and silver-bearing polymetallic veins of intermediate sulfide composition that conformed an outcropping porphyry system
3
at Chita and a lithocap of a porphyry system at Chinchillones. San Juan Province of Argentina has a robust mining sector and recognizes the important economic benefits of responsible development of its substantial Mineral Resource endowment.
About Minsud Resources Corp.
Minsud is a mineral exploration company focused on exploring its flagship Chita Valley Cu-Mo- Au-Ag Project, in the Province of San Juan, Argentina. The Company also holds a 100% owned portfolio of selected early stage prospects, including 6,000 ha in Santa Cruz Province, Argentina.
FOR FURTHER INFORMATION PLEASE CONTACT
Ramiro Massa
President and Chief Executive Officer [email protected] +1 416-479-4466
CAUTIONARY STATEMENT REGARDING FORWARD-LOOKING INFORMATION:
This news release includes certain information that may constitute forward-looking information under applicable Canadian securities laws. Forward-looking information includes, but is not limited to, statements about strategic plans, spending commitments, future operations, results of exploration, anticipated financial results, future work programs, capital expenditures and objectives. Forwardlooking information is necessarily based upon a number of estimates and assumptions that, while considered reasonable, are subject to known and unknown risks, uncertainties, and other factors which may cause the actual results and future events to differ materially from those expressed or implied by such forward-looking information including, but not limited to: fluctuations in the currency markets (such as the Canadian dollar, Argentina peso, and the U.S. dollar); changes in national and local government, legislation, taxation, controls, regulations and political or economic developments in Canada and Argentina or other countries in which the Corporation may carry on business in the future; operating or technical difficulties in connection with exploration and development activities; risks and hazards associated with the business of mineral exploration and development (including environmental hazards or industrial accidents); risks relating to the credit worthiness or financial condition of suppliers and other parties with whom the Company does business; presence of laws and regulations that may impose restrictions on mining, including those currently enacted in Argentina; employee relations; relationships with and claims by local communities; availability and increasing costs associated with operational inputs and labour; the speculative nature of mineral exploration and development, including the risks of obtaining necessary licenses, permits and approvals from government authorities; business opportunities that may be presented to, or pursued by, the Company; challenges to, or difficulty in maintaining, the Company’s title to properties; risks relating to the Company’s ability to raise funds; and the factors identified under “Risk Factors” in the Company's Filing Statement dated April 27, 2011. There can be no assurance that such information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such information. Accordingly, readers should not place undue reliance on forward-looking information. All forward-looking-information contained in this news release is given as of the date hereof and is based upon the opinions and estimates of management and information available to management as at the date hereof. The Company disclaims any intention or obligation to update or revise any forward-looking information, whether as a result of new information, future events or otherwise, except as required by law.
4
Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.
5