Ibero Mining Corp. Interim / Quarterly Report 2023

Aug 29, 2023

47469_rns_2023-08-28_b4105f2b-8403-4fb5-becd-34762e26ac1f.pdf

Interim / Quarterly Report

Open in viewer

Opens in your device viewer

Europacific Metals Inc. (formerly Goldplay Mining Inc.) Management Discussion and Analysis For the three and six months ended June 30, 2023 (Expressed in Canadian dollars)

SKEENA RESO

EUROPACIFIC METALS INC. Management Discussion and Analysis June 30, 2023

MANAGEMENT DISCUSSION AND ANALYSIS Period ended June 30, 2023

INTRODUCTION

The Management Discussion & Analysis has been prepared by management and reviewed and approved by the Board of Directors on August 28, 2023. The following discussion of performance, financial condition and future prospects should be read in conjunction with the unaudited condensed consolidated interim financial statements and the related notes thereto for the three and six months ended June 30, 2023 and 2022, and in conjunction with the audited annual consolidated financial statements and the related notes thereto for the years ended December 31, 2022 and 2021. The information provided herein supplements but does not form part of the condensed consolidated interim financial statements. This discussion covers the six-month period ended June 30, 2023 and the subsequent period up to August 28, 2023, the date of issue of this MD&A. Monetary amounts in the following discussion are in Canadian dollars unless otherwise noted. Additional information regarding the Company can be found on the Company’s page at www.sedar.com.

This MD&A contains Forward Looking Information. Please read the Cautionary Statements on page 3 carefully.

2

EUROPACIFIC METALS INC. Management Discussion and Analysis June 30, 2023

FORWARD LOOKING STATEMENTS

This MD&A contains certain forward-looking statements or forward-looking information within the meaning of applicable Canadian securities laws. All statements and information, other than statements of historical fact, included in or incorporated by reference into this MD&A are forward-looking statements and forward-looking information, including, without limitation, statements regarding activities, events or developments that we expect or anticipate may occur in the future. Such forward-looking statements and information can be identified by the use of forward-looking words such as "will", "expect", "intend", "plan", "estimate", "anticipate", "believe" or "continue" or similar words and expressions or the negative thereof. There can be no assurance that the plans, intentions or expectations upon which such forward-looking statements and information are based will occur or, even if they do occur, will result in the performance, events or results expected.

The forward-looking statements and forward-looking information reflect the current beliefs of the Company, and are based on currently available information. Accordingly, these statements are subject to known and unknown risks, uncertainties and other factors which could cause the actual results, performance or achievements of the Company to be materially different from any future results, performance or achievements expressed in or implied by the forwardlooking statements. This forward-looking information includes estimates, forecasts, plans, priorities, strategies and statements as to the Company’s current expectations and assumptions concerning, among other things, its exploration and development plans, its ability to access sufficient funds to carry on operations, compliance with current or future regulatory regimes, particularly in the case of ambiguities, financial and operational performance and prospects, collection of receivables, anticipated conclusions of negotiations to acquire projects or investments, our ability to attract and retain skilled staff, expectations of market prices and costs, expansion plans and objectives, requirements for additional capital, the availability of financing, and the future development and costs and outcomes of the Company’s projects or investments. The foregoing list of assumptions is not exhaustive. Events or circumstances could cause actual results to vary materially.

We caution readers of this MD&A not to place undue reliance on forward-looking statements and information contained herein, which are not a guarantee of performance, events or results and are subject to a number of risks, uncertainties and other factors that could cause actual performance, events or results to differ materially from those expressed or implied by such forward-looking statements and information. These factors include: results of exploration programs, management's discretion to reallocate its working capital, unanticipated future operational difficulties (including cost escalation, unavailability of materials and equipment, industrial disturbances or other job action and unanticipated events related to health, safety and environmental matters); social unrest; failure of counterparties to perform their contractual obligations; changes in priorities, plans, strategies and prospects; general economic, industry, business and market conditions; disruptions or changes in the credit or securities markets; changes in law, regulation, or application and interpretation of the same; the ability to implement business plans and strategies, and to pursue business opportunities; rulings by courts or arbitrators, proceedings and investigations; inflationary pressures; and various other events, conditions or circumstances that could disrupt the Company’s priorities, plans, strategies and prospects including those detailed from time to time in the Company’s reports and public filings with the Canadian securities administrators, filed on SEDAR .

This information speaks only as of the date of this MD&A. The Company undertakes no obligation to revise or update forward-looking information after the date of this document, nor to make revisions to reflect the occurrence of future unanticipated events, except as may be required under applicable securities laws or the policies of the TSX-Venture Exchange.

3

EUROPACIFIC METALS INC. Management Discussion and Analysis June 30, 2023

THE COMPANY

Europacific Metals Inc. (“Europacific” or the "Company”) was incorporated under the Business Corporations Act (British Columbia) on June 16, 2017. Europacific is a public company, listed on the TSX Venture Exchange (the “TSXV”) under the symbol “EUP”, the Frankfurt Stock Exchange (“FSE”) under the symbol “9FY” and the OTC Market Exchange under the symbol "AUCCF".

Europacific holds several brownfield gold, and copper-gold projects located in Portugal with near term mining potential.

RECENT EVENTS

Strategic decision to pursue Portuguese exploration projects and terminate the Canadian options

In November 2022, the Company undertook a strategic review of its exploration projects and results of exploration programs and decided to focus its exploration efforts on the Portuguese projects, which are seen as having a greater potential and being a better fit for the Company. The Company does look at the European and Eurasian geological setting as highly prospective geologically, and at a time when the European Union (“EU”) realizes their members must look within the EU borders as a source for basic and rare industrial metals. The region boasts high standards, all weather, civil and power infrastructure, a highly educated workforce, and motivated geological professionals with excellent country knowledge. As a result of this decision, at the end of 2022, the Company terminated its mineral options for the properties located in British Columbia (“BC”). See “MINERAL PROPERTIES” section below for details of the Company’s Portuguese and terminated BC projects.

On January 6, 2023, reflecting focus on European and Eurasian geological opportunities, the Company changed its name from Goldplay Mining Inc. to Europacific Metals Inc.

Letter of Agreement with Portuguese State Owned Mining Company

The Company signed a Letter of Agreement (the “LOA”) with Empresa de Desenvolvimento Mineiro SA (“EDM”), a State owned mining company, in regards to an application submitted for a new exploration concession totaling 137 square kilometers (“Monte das Mesas “ or “the Property”) located in the world-class VMS district in the Iberian Pyrite Belt (“IBT”). The Property holds great potential to host significant base and precious metals mineralization.

The LOA was signed by Europacific and EDM on April 7, 2022 and the project’s exploration application was filed with the Portuguese Mines Department on May 6, 2022. A consortium agreement will be signed upon granting of the mineral rights. EDM will participate with 15% and Europacific with 85% in the consortium. EDM will have a free carried interest in the consortium until Europacific has completed a total of 650,000 Euro in exploration costs. This amount represents the total of EDM’s previous exploration expenditures on the property. Future exploration costs in excess of 650,000 Euro will be funded by each party on proportional basis.

Management changes

In order to further advance Company’s existing portfolio of projects in Portugal and beyond, Mr. Christopher Osterman was appointed as the Company’s Chief Executive Officer effective August 4, 2022. Mr. Catalin Kilofliski (former CEO), was appointed as Europacific’s Executive Chairman and will continue to lead Company’s strategy. Europacific’s current Chair of the Board, Dr. Deepak Malhotra was appointed as Lead Independent Director.

4

EUROPACIFIC METALS INC.

Management Discussion and Analysis June 30, 2023

MINERAL PROPERTIES

The following tables provide a breakdown of the mineral properties assets as of June 30, 2023 and exploration expenses of Europacific for the six month periods ended June 30, 2023 and 2022 :

Mineral properties:

==> picture [472 x 162] intentionally omitted <==

Exploration expenses:

==> picture [472 x 170] intentionally omitted <==

5

EUROPACIFIC METALS INC.

Management Discussion and Analysis June 30, 2023

==> picture [472 x 201] intentionally omitted <==

A. Borba 2

On April 15, 2021, the Company finalized the acquisition of 70% of EVX Portugal, a private based Portuguese company who has the legal rights to an exploration license application with the Portugal Government to the Borba 2 exploration property (the “Exploration Application”), covering approximately 328.5 square kilometres in the Alentejo region in Southern Portugal. On October 28, 2021, the Exploration Application was approved by the Portuguese government. Europacific, through its subsidiary, EVX Portugal, entered into an exploration/concession agreement with the Portuguese government in relation to the Borba 2 property.

On the acquisition date, EVX Portugal had net assets of approximately $NIL, as such, for the purpose of purchase price allocation, the entire amount ($17,994) paid by Europacific to acquire the 70% interest in EVX Portugal was recorded as the acquisition cost on Europacific’s Consolidated Statement of Financial Position, part of the Exploration and evaluation assets. As per the purchase agreement, when the exploration license to Borba 2 was granted by the Portuguese government, Europacific paid an additional cash of $45,686 and issued common shares valued at $20,000 to the sellers. Both amounts recorded as the acquisition cost on Europacific’ Statement of Financial Position, part of the Exploration and evaluation assets. For accounting purposes, the acquisition has been recorded as an asset acquisition as EVX Portugal did not meet the definition of a business, as defined in IFRS 3 Business Combinations . On April 25, 2023, the Company and European Electric Meals Inc entered into an agreement pursuant to which the Company will purchase the 30% interest that European Electric Metals Inc has in EVX Portugal for $50,000 and 700,000 common shares of the Company. The transaction was approved by the TSX-V on July 24, 2023.

The Exploration Application has a well-documented potential to host precious and base metals mineralization often enhanced by the presence of abundant Au and /or Cu mineral occurrences in shear zones and in epithermal systems associated with intra-Ordovician volcanics. The Exploration Application includes a total of four separate projects including three past producing mines that covers an area of 328.5 square kilometers as follows:

1. Miguel Vacas- Past Producing Copper Mine

The copper mine last operated in 1986 and has produced at an average grade of 1.2-1.4% Cu. Historical near surface drilling (60 to 71.63m) intercepted 1.79 % Cu over 10.54m including 2.29% Cu over 7.30 m.

A historical non-compliant in-house resource estimation was completed by Rio Narcea in 2007 based on 20 historical holes and estimated:

  • Oxide ore (from 0 to 80m depth): 1.2 Mt @ 1.23% Cu.

6

EUROPACIFIC METALS INC. Management Discussion and Analysis June 30, 2023

  • Sulphide ore (from 80m to 250m): 4.4 Mt @ 1.24% Cu

  • The project remains open for exploration. This mineralised system is open in all directions and at depth.

The readers should not rely on any historical estimates. The Company and the QP has not done sufficient work to classify historical estimate as a current resource. Company is not treating the historical estimate as a current resource. Additional work including drilling will be required to verify and upgrade historical estimates.

2. Mostardeira Copper-Gold Mine

This Cu-Au mine area, located approximately 2 km south of the town of Estremoz represents a wide WSW-ESE shear zone that is developed for at least 700 m along strike and is open into both directions. This shear zone has been historically mined for Cu with most of the mining works concentrated along a thin high-grade Cu zone (<2m) averaging over 5% Cu. Gold was also recovered from arsenopyrite rich zones within the vein system.

Mineralization is hosted by Silurian and Devonian metasediments. Channel sampling by Rio Narcea (2006) has intercepted the following mineralized intervals: 2.60m grading 4.15 g/t Au, 0.40% Cu including 0.60m grading 11.20 g/t Au and 0.65 % Cu and another 3.60m interval grading 2.40 g/t Au, 0.82 % Cu and 80 g/t Ag. The average grade for the total of 34 samples analysed was 1.54 g/t Au, 22 g/t Ag and 0.25% Cu with a maximum of 11.20 g/t Au and a minimum of 0.10 g/t Au.

A total of 4 holes were drilled by MAEPA in 2007 (total 485m) in the main Mostardeira workings. Highlights of the mineralised intercepts include: 1m grading 2.8 g/t Au, 5.9 g/t Ag and 0.18% Cu from 122.5m and 1.5 m grading 0.99 g/t Au , > 00 g/t Ag and 3.98% Cu from 177m (Hole MM1); 1m grading 5.72 g/t Au, 78.9 g/t Ag from 43.7m (Hole MM2); 0.5m grading 0.84 g/t Au, 27.1 % Ag, 3.89 % Cu from 26.3m and 1m grading 1m grading 6.8 g/t Au, 12.8 g/t Ag from 40.5m (Hole MM2A); 0.7m grading 5.28 g/t Au, 1 g/t Ag from 100.6m, and 1m grading 1.26 g/t Au, 18.5 g/t Ag and 1.14% Cu from 114.3m (Hole MM3).

The project is open for exploration.

3. Bugalho Copper-Gold Mine

Dump samples of silicified and sheared acid tuffs from the Bugalho mine area assay up to 10.97 g/t Au, 5.36% Cu and 20 g/t Ag.

Mineralization can be mapped about 5 km along strike and includes three main veins up to 1.3m thick within a several meter wide shear zone.

The project is open for exploration.

4. Almagreira Gold Prospect

This area has been identified by Rio Tinto during the early eighties and limited trenching and drilling have indicated the presence of gold mineralization associated with clay-sericite-silica alteration zones associated with a ENE-WSW fracture zone and represents an epithermal system identified in this sector hosted by brecciated acid volcanics and dolomites.

Historical drilling intercepted an interval of 5.45 m grading 1.53 g/t Au, including 2.47m grading 2.44 g/t Au from hole PAM-01. The highest individual value obtained came from a gossanous quartz-dolomite altered marble grading 5.77 g/t Au over an intercept of 0.75m. Hole PAM-02 intercepted an interval of 2m grading 3.7 g/t Au. The mineralized zone coincides with sections of intense silica-carbonate alteration with several massive gossan zones and localized fresh sulphide dissemination (chalcopyrite and pyrite).

The project is open for exploration.

For additional details on Borba 2, please see the 43-101 technical report that the Company issued in April 2023.

7

EUROPACIFIC METALS INC. Management Discussion and Analysis June 30, 2023

B. Barrancos

On June 23, 2021, the Company signed a definitive agreement (the “Agreement”) to acquire up to 100% equity interest in a private Portuguese company, Indice Crucial, which holds exploration rights on several past producing copper and gold projects as well as other advanced gold exploration applications in Portugal. Upon signing of the Agreement, Europacific has 20% ownership in Indice Crucial. Under the terms of the Agreement, Europacific will acquire up to a 100% equity interest in Indice Crucial by making the following cash and share payments to BMP Holding SGPS LDA, the parent of Indice Crucial.

Timing Cash in Euro Europacific Shares Europacific ownership
Upon Signing 100,000 (paid June 23,
2021)
100,000 (issued July 19,
2021)
20%
Within 2 Years 150,000 500,000 50%
Within 4 Years 100,000 750,000 85%

Europacific, can acquire the remaining 15% equity interest, for a total of 100%, at any time, for 2 million Euro. The 20% initial investment in Indice Crucial was recorded at cost $(165,987) as a significant influence investment on the Statement of Financial Position of the Company

The Barrancos project is located in south Central Portugal, near the Spanish border and cover an area of 74 square kilometers. Exploration rights were secured by Indice Crucail from the Portuguese Government Mining division in 2020. The exploration license allows the exploration work on Barrancos to be undertaken (including drilling) for a period of up to 5 years.

Barrancos includes several past producing gold and copper mines, including two more advanced drill ready copper and gold projects as follows:

1. Aparis Copper Mine

In November 2021, Europacific commenced drilling on the Aparis Copper Mine (“Aparis”). Aparis is a past producing underground copper mine that produced until 1975 when copper averaged just $0.55 per pound. The buildings and a small flotation mill remain on site. The mine contains an extensive vein system. The system extends for over 3 km along strike and remains open for exploration. Historical underground results include:

  • 47 metres averaging 3.09% Cu

  • 40 metres averaging 3.04% Cu

  • 62 metres averaging 2.21% Cu

The historic mine has been developed to a depth of just 220m and produced copper concentrate averaging up to 35% Cu. Along with Aparis, the area includes multiple other small-scale copper and gold showing that deserve further investigation and modern exploration.

Recent exploration carried out by Europacific Metals has been focused in the Aparis copper mine and in the Lirio goldcopper prospect. Aparis drilling results highlight a broad mineralized zone as indicated by an excellent intercept of 1.18 % Copper over 12.2 meters from 207.0m, including 2.33% Cu over 5.50m and including 5.50% Cu over 2m. This zone has been mapped over 2.5 km along strike, with potential to extend up to 5 km.

The Company commenced the exploration in Q42021 (please the “Exploration results” section below).

8

EUROPACIFIC METALS INC. Management Discussion and Analysis June 30, 2023

2. The Lírio Gold Project

The Lirio Gold Project (“Lirio”) is a very prospective and under explored gold system which has indications of being an extensive volcanic breccia gold system based on historical drilling, detailed surface sampling and the general geology of the area. Historical sampling at Lirio have returned results of:

  • up to 125g/t Au from chip samples and up to 7.7g/t Au from channel samples

  • drill hole KBL-01 intersected 7.19 g/t Au and 0.63% Cu over 5.52 metres, including 17.8 g/t Au and 0.25% Cu over 2.03 metres

A very limited drilling campaign was carried out in 2008 by the Rio Narcea/Kernow joint venture, that intersected the mineralized zone below the main zone of the shallow underground workings. Scout hole GBA2201 drilled by Europacific Metals confirms the presence of significant mineralization with a shallow drilling intercept of 3 m grading 3.56 g/t Au from 17m, 1m grading 1.17 g/t Au from 64.5m and 2m grading 3.45 g/t Au from 128.5m.

3. Bigorne Gold Exploration Application

The Bigorne Gold Exploration Application (“Bigorne”) is an exploration/concession application made by Indice Crucial directly with the Portuguese Government Mining Division. Bigorne is situated in northern-central part of Portugal and covers an area of 24 km[2] . The main prospect includes a wide sheeted vein system, oriented N-S to NNE-SSW, hosted in Variscan granites from a suite of syn-to pos-tectonic intrusions.

A total of 15 historical holes have been drilled in several sections of the shear corridor with an indication of a bulk mineable potential as suggested by some of the best intercepts including:

  • 40.2m grading 1.10 g/t Au from 35m, Including 10m grading 2 g/t Au in hole BI-1;

  • 13m grading 1.66 g/t Au from 53m, including 6m grading 2.32 g/t Au in hole BI-3;

  • 27m grading 1.0 g/t Au from 36m, including 5m grading 1.53 g/t Au in hole BI-4 and

  • 13m grading 1.61 g/t including 4m grading 2.48 g/t Au from 39m in hole BI-5.

4. Vilariça Gold Exploration Application

The Vilarica Gold Exploration Application (“Vilarica”) is an exploration/concession application made by Indice Crucial directly with the Portuguese Government Mining Division. The project covers a total of 178 km[2] is situated approximately 200 km east of Porto and 450 Km northeast of Lisbon. The area is covered by an alloctonous sequence of metasediments and metavolcanics that have been extensively intruded by Variscan granites. These are in contact with a mafic/ultramafic complex in the NE.

Numerous vein and disseminated type showings and small diggings for Gold, Silver, Lead and Zinc occur thoroughly associated with intrusion/volcanic activity together with Tin and Tungsten respectively in greisen and skarn deposits. All these are spatially related with deep-seated post-Variscan structures with the Vilariça fault interpreted to represent the main structural feature. This area is adjacent to a gold mining district including Latadas and Freixeda mine areas located only a few kilometers to the west of the permitted mine owned by the Minaport group.

9

EUROPACIFIC METALS INC. Management Discussion and Analysis June 30, 2023

Exploration results - Aparis Phase 1

In November 2021 Europacific commenced exploration on the Barrancos properties. Europacific’s board of directors approved an initial budget of Euro 447,000 for the first exploration phase. This initial drilling campaign for approximatively 1,000m and additional exploration work was focused on expanding and better defining the mineralization for a wider copper zone (> 1% Cu) within the Aparis shear zone that currently averages more than 10m in true thickness. The Aparis deposit is a broad metalliferous (Cu-Ag) shear zone hosted in a Devonian turbidite sequence (Terena Formation). The mineralized system is interpreted to be genetically associated with a late Devonian hypabyssal bimodal magmatic suite and breccia systems that also contain high-grade gold values in other target areas that are presently being assessed.

HIGHLIGHTS

  • Drill intercept: 1.18 % Copper (“Cu”) over 12.2 meters (“m”) from 207.0m, including 2.33% Cu over 5.50m and including 5.50% Cu over 2m.

  • Discovery of a broad mineralized copper zone, immediately adjacent at depth to the old mining works

  • Excellent exploration upside. Extensive copper mineralized vein system mapped over 2.5 km along strike, with potential to extend up to 5 km.

  • Discovery of a gold-bearing structure, 140 m west of the copper zone, averaging 5.87 grams per tonne (“g/t”) gold over 2 m

  • Historic Mine located less than 160Km (over paved roads) to a large copper smelter located in Huelva

DETAILS OF RESULTS

The copper mineralized system occurs at the Aparis mine that is much wider than the previous mining activities indicate. Furthermore, the discovery of a gold-bearing structure within 140 m of the copper zone further enhances the potential of the project. Assay results have been received from all three diamond holes from the Phase 1 drilling campaign for a total of 824 m.

The results confirm the presence of a wide (>10m) copper mineralized envelope as indicated by the most recent results which include a 12.2m interval grading 1.18% Copper in hole GBA2103 with several sections of high-grade including 5.5m averaging 2.33% and including 2.0 m of 5.5% Cu (as indicated in the table below). In addition, a new auriferous zone has been identified 140 m west of the main vein system which returned 5.87 g/t Au over 2m in hole GBA2101

10

EUROPACIFIC METALS INC. Management Discussion and Analysis June 30, 2023

Table 1 – Significant Drill Results, Aparis Copper Mine

Drill Hole From (m) To (m) Drilled
*Width(m) **
Cu (%) Au (g/t) Structure
GBA2101** 46.05 48.05 2.00 --- 5.87 140 west of Main vein
and 295.00 300.50 5.50 0.21 --- Main vein
and 318.50 321.50 3.00 0.31 --- Parallel vein
GBA2102 No significant results - old mine stope [email protected] m
GBA2103 212.40 219.20 12.20*** 1.18 --- Main vein
including 213.70 219.20 5.50 2.33 --- Main Vein
including 213.70 215.70 2.00 5.50 --- Main Vein
  • True widths have not been determined as the mineralized body remains open. Further drilling is required to determine the mineralized body orientation and true widths.

Analytical results from Hole GBA2101 were previously reported. Refer to press release dated February 28, 2022 *Adjacent to 2.4 m of historically mined stope (210 – 212.4 m)

The Aparis Mine was operated as a small scale mine from 1889 to 1927 and more recently between 1969 and 1975 when the mine closed due to low copper prices.

Aparis consists of a main vein zone (Saramago vein) that has been traced through surface exposures and mostly shallow underground workings for more than 2.5 km along a north-northeast strike and dipping steeply to the west. Historical mining focused on a narrow (<1m wide), very high-grade portion of the vein zone, where grades were reported to reach in excess of 10% Cu. The deepest parts of the mine are 220 m below surface, below which very little historical exploration took place. Further north, historical workings at the Malhada dos Caeiros and Vale de Marcos mines (Figure 1) did not extend much below 50 m depth. In addition, the full width potential of the main vein zone has never been thoroughly tested by drilling and is believed to be upwards of 10m wide.

Europacific drill tested the vein system from November 2021 to February 2022 with a total of 3 holes to investigate in detail the grades, nature, and potential for broader zones and depth extension of the mineralized system. This will help us evaluate possible scenarios of developing a modern mining operation by contrast with the artisanal methods used in the past, with historical production coming exclusively from <1m thick high-grade veins.

11

EUROPACIFIC METALS INC.

Management Discussion and Analysis June 30, 2023

Figure 1 – Location of Drill Holes and Historic Workings at the Aparis Copper Mine

==> picture [496 x 352] intentionally omitted <==

Drill Hole GBA2101 targeted the main vein zone at approximately 260 m depth and 90 meters below the historical workings. The hole intersected two parallel vein structures, grading 0.21% Cu over 5.5 m from 295m drilled depth and 0.31% Cu over 3m from 318.5m drilled depth. These results are encouraging in that they show the copper mineralized structures are wide and continuous at depth and that additional drilling is needed to vector in on potential highergrade shoots within the structures. As previously reported, this same hole also intersected a previously unknown goldbearing zone, approximately 140 m west of the main copper vein zone grading 5.87 g/t Au over 2m , from 46.05m drilled depth

Drill Hole GBA2102 was collared approximately 180 m south of GBA2101 and drilled through a series of historic mining works (that have not been previously identified). The hole was therefore stopped at a vertical depth of approximately 80 m. It is believed that significant copper grades may have been historically mined from these old stopes. Based on old mining records this target area was reported to run 4.75% Cu over 0.82m.

Drill Hole GBA2103 was collared approximately 230 m north of GBA2101 and was the furthest north hole drilled by the Company. The hole intersected a 12.2m interval averaging 1.18% Cu, including several higher-grade sections, as shown in Table 1. The interval includes a 2.4 m drilled length through an historical mine stope where no core was recovered, and a 0.00% Cu grade assigned to the interval. Immediately east of the stope the drill hole returned the

12

EUROPACIFIC METALS INC.

Management Discussion and Analysis June 30, 2023

highest copper grades, including 9.69% Cu over 1m, 5.50% Cu over 2m and 2.33% Cu over 5.50 m. This intercept is suggesting that significant copper mineralization still remains unmined. The old workings were focused on thin highgrade sections (>3% Cu typically) leaving behind a large of the mineralized material. As shown in Figure 2 the drill hole crossed the mineralized structure neartthe deepest part of the historical mine at a vertical depth of approximately 200 m, indicating good potential for the mineralization to continue at depth and towards the north.

Figure 2 – Cross Section (looking North) Showing Drill Hole GBA2103 and Historical Mine Workings

==> picture [430 x 314] intentionally omitted <==

Exploration focus will be put on drilling continuation on the depth and strike extensions of the known mineralization and evaluation of wider zones than those historically mined, better tailored to the present technologies and higher metal prices.

==> picture [481 x 111] intentionally omitted <==

13

EUROPACIFIC METALS INC. Management Discussion and Analysis June 30, 2023

Table 2: Drill Hole Summary

Drill Hole Easting
(UTM)
Northing
(UTM)
Elevation
(m)
Azimuth
(degrees)
Dip
(degrees)
Length
(m)
GBA2101 668200 4221334 233 115 -60 359.30
GBA2102 668246 4221150 225 110 -45 150.00
GBA2103 668357 4221566 235 110 -70 315.00
TOTAL 834.3

All samples were sent to ALS Global Laboratories in Spain for sample preparation and analysis. At the laboratory, rock sample preparation involved drying, fine crushing to better than 70% passing minus 2 mm (CRY-31), then split the sample using a Boyd Rotary Splitter (SPL-22Y) and pulverizing a 1000g split to 85% passing the <75 microns (PUL-32). The fine fraction was analyzed for gold by Fire Assay on a 30g aliquot with an ICP-AES finish (Au-ICP21), and for 48 additional elements by four acid digestion and inductively coupled plasma (“ICP”) - ultra trace level analysis (MEMS51). Quality control samples were regularly analyzed by the laboratory and include blanks (CDN-BL-10) and, certified reference materials (CDM-CM-41) provided by CDN Resources Laboratories Ltd, #2, 20148 – 102nd Ave, Langley, B.C., Canada.

Future Exploration Plans

The Company’s review of historical exploration and mining records indicate that historical miners have focused on narrow (<1m), high grade copper structures, often in excess of 10% Cu, while leaving behind the surrounding, lower grade material (1% to 3% Cu), which at the time may not have been considered economic. Europacific drill hole GBA2103 proved the presence of a wider mineralized system.

The potential quantity and grade of the Company’s exploration target is conceptual in nature. There has been insufficient exploration to define a mineral resource and it is uncertain if further exploration will result in the target being delineated as a mineral resource.

With Phase 1 complete, the Company proposes two additional follow-up drill programs with the following goals and objectives:

Phase 2 (2,500m in drilling, 10 holes):

  • Drill confirmation of reported high grade zones from old reports and expand the “mining widths” to a more substantial target size.

  • Check depth extensions to the mineralized system below reported known ore shoots

Phase 3 (6,500m in drilling, 20 holes):

  • Infill drilling on a ca. 200 x 200m grid to come out with a preliminary resource estimation (Inferred category);

  • Mineralogical and metallurgic tests of composite core samples on an independent laboratory.

  • Based on results undertaking of a PFS considering at this stage several possible mining scenarios.

  • Preparation of a preliminary Environmental Impact Study (EIS) is also considered along with a decision to proceed with the application for a mining license will be taken during this period.

14

EUROPACIFIC METALS INC. Management Discussion and Analysis June 30, 2023

Figure 3 – Longitudinal Section (looking West) Along the 2.5km Length of the Main Vein System Showing Phase 1 and Proposed Phases 2 and 3 Drilling

==> picture [498 x 291] intentionally omitted <==

The potential quantity and grade of the Company’s exploration target is conceptual in nature, there has been insufficient exploration to define a mineral resource and t it is uncertain if further exploration will result in the target being delineated as a mineral resource.

For additional details on Barrancos, please see the 43-101 technical report that the Company issued in January 2023.

C. Scottie Gold Project

On August 19, 2022 the Company signed an Option Agreement with Scottie Resources Corp. (“Scottie”), a company engaged in the exploration and evaluation of gold and silver properties located in the “Golden Triangle” of British Columbia, to purchase an working interest in Scottie’s exploration properties (the "Option").

Under the terms of the agreement, Europacific can acquire up to 3.75% interest in the Scottie’s properties by incurring up to $1,500,000 in flow through eligible exploration expenses until December 31, 2022. If the exploration expenses incurred amount to less than $1,500,000, Europacific’s earned interest in the Scottie’s properties will be reduced proportionally.Following the exercise of the Option, Europacific will have the right (the “Put Right”) to require Scottie to repurchase the interest earned by Europacific by paying cash, at a price calculated by dividing the total exploration expenditures incurred by Europacific by 1.71. Following the exercise of the Option, Scottie will have the right (the “Call Right”) to repurchase the interest earned by Europacific by paying cash, at a price calculated by dividing the total exploration expenditures incurred by Europacific by 1.71.

In the event the Put Right or the Call Right is exercised, Scottie may, in its sole discretion, satisfy up to $300,000 of the price for the repurchase of Europacific’s interest by issuing Europacific common shares in the capital of Scottie.

15

EUROPACIFIC METALS INC. Management Discussion and Analysis June 30, 2023

In October 2022, the Company fulfilled its expenditure commitment by incurring a total of $1,580,000 flow-through eligible expenditures and exercised the option to acquire the working interest in the Scottie’s properties.

In order to make cash available for its Portuguese projects, which are seen as having a higher potential by Company, on November 9, 2022, the Company exercised the Put Right and resold the working interest to Scottie for a cash payment of $900,000 received on November 10, 2022.

D. Scottie West Property Option

On November 22, 2020, the Company entered into a definitive agreement with Roughrider to acquire a 70% interest in the Scottie West Property, located in the “Golden Triangle” in Northwestern British Columbia.

Pursuant to terms of the agreement with Roughrider, the Company has committed to the following to earn the 70% interest in the Scottie West property:

Cash Shares to be issued to
Roughrider
Work commitment
Upon Signing $25,000 (paid
in November
2020)
Equivalent of $25,000 (issued in
November 2020)
none
Year 1 $25,000 (paid
in November
2021)
Equivalent of $50,000 (issued in
November 2021)
$200,000 (fulfilled)
Year 2 $50,000 Equivalent of$75,000 $100,000
Year 3 $150,000 Equivalent of$150,000 $300,000
Year 4 $250,000 Equivalent of$200,000 $400,000
Total $500,000 Equivalent of$500,000 $1,000,000

In November 2022, the Company decided to terminate the Scottie West option and not further pursue this project. The Company has made the decision to focus its exploration efforts on the Portuguese projects.

E. Big Frank and Goldstorm South properties

On August 31, 2021, the Company signed an option agreement with Cazador Resources Ltd. (“Cazador”) to earn a 100 % interest in two properties known as "Big Frank" and "Goldstorm South" (formerly Nuit Mountain). The projects are located in the western Chilcotin District of southwestern British Columbia.

The terms of the agreement are as follows:

Big Frank

Big Frank
Cash Shares to be issued to
Cazador
Work commitment
Upon Signing $10,000
(paid in
August
2021)
60,000 (issued in
September 2021)
$ 50,000 before
December 31, 2021
(fulfilled)
Year 1 – before August 31,
2022
$40,000 140,000 $350,000
Year 2 – before August 31,
2023
$100,000 600,000 $600,000

16

EUROPACIFIC METALS INC.

Management Discussion and Analysis June 30, 2023

Year 3 – before August 31,
2024
$150,000 1,200,000 $2,000,000
Year 4 – before August 31,
2025
$400,000 2,000,000 $4,000,000
Total $700,000 4,000,000 $7,000,000

Goldstorm South

Cash Shares to be issued to
Cazador
Work commitment
Upon Signing $5,000
(paid in
August
2021)
30,000 (issued in
September 2021)
$ 25,000 before
December 31, 2021
(fulfilled)
Year 1 – before August 31,
2022
$20,000 70,000 $175,000
Year 2 – before August 31,
2023
$50,000 300,000 $300,000
Year 3 – before August 31,
2024
$75,000 600,000 $1,000,000
Year 4 – before August 31,
2025
$200,000 1,000,000 $2,000,000
Total $350,000 2,000,000 $3,500,000

In November 2022, the Company decided to stop exploration activities on Big Frank and Goldstorm South to focus its exploration efforts and resources in the near future on the Portuguese projects.

FINANCING ACTIVITIES

On April 11, 2022, Europacific completed a private placement financing and issued 1,000,000 common shares for toal proceeds of $150,000 ($0.15 per share). No compensation was paid in connection with this financing.

SUMMARY OF QUARTERLY RESULTS

Quarter ended 30-June-23 31-Mar-23 31-Dec-22 30-Sept-22
Revenue(1) - -
Loss for the quarter $ (177,905) (205,124) $ (1,053,188) $ (117,367)
Loss per share $ (0.00) (0.00) $ (0.02) $ (0.00)
Quarter ended 30-June-22 31-Mar-22 31-Dec-21 30-Sept-21
Revenue(1) - - - -
Loss for the quarter $ (301,489) (310,030) $ (228,430) $ (442,262)
Loss per share $ (0.01) (0.01) $ (0.01) $ (0.01)

1this being a Company without a revenue generating business, there are no revenues from operations or investments;

17

EUROPACIFIC METALS INC. Management Discussion and Analysis June 30, 2023

Losses for the six months ended June 30, 2023

Losses of $383,029 incurred during the six months ended June 30, 2023 (“H1 2023) are lower than losses of $611,519 for the six months ended June 30, 2022 (“H 12022”). The table below summarizes the H1 2023 costs in comparison to H1 2022:

H1 2023 H1 2022 Variance Explanation for variance
CFO and corporate secretary fees; consistent
Accountingand corporate secretarial fees $ 30,250 $ 33,000 $ (2,750) in bothperiods
Audit and tax fees 29,300 14,825 14,475 Additional tax advice in H1 2023
Higher amounts incurred in H1 2022 in
relation to evaluation of potential projects of
Consultingand due diligence 50,117 82,500 (32,383) interest
Hiher amounts spent in H1 2023 because of
mining conferences and expenses incurred in
Corporate development (includes investor relations relation to seeking new opportunities in
and shareholder communications) 134,685 36,590 98,095 Europa and Asia
Depreciation of computer equipment in
Depreciation 737 - 737 H12023
Legal fees 3,132
10,451 (7,319) Miminam legal fees incurred bothperiods
Allocation of executive director and CEO fees
to exploration projects and corporate
development expenses in H1 2023 resulted in a
lower recorded accouting amount for the
Management 42,891 53,334 (10,443) management fees
Marketing 713 75,501 (74,788) Minimal marketingactitivities in H1 2023
No stock options issued in H12023, therefore
no stock based compensation to account for in
Share based compensation - 85,788 (85,788) H12023
Higher expenses incurred in H1 2022
including office space and foreign exchange
Office and administration expenses 12,974
42,255 (29,281) losses on intercompanyloans
See MINERAL PROPERTIES section above for a
breakdown of expenses by property and by
period; higher exploration expenses incurred
in H1 2022 when the Company had in its
portfolio the BC projects of which it disposed
Exploration and evaluation 68,850 126,962 (58,112) in Q4 2023
Regulatory,exchange listingand transfer agent fees 21,933 26,701 (4,768) Consistent in bothperiods
Flow through liability expenditures incurred
mainly in the second part of 2022, with a
smaller amount incurred in H1 2022 and nil in
Recoveryof flow-through liability - (7,297) 7,297 H1 2023
Smaller amount spent on Barrancos in H1
2023, therefore a smaller management fee
Management fee income (1,068) (4,059) 2,991 charged to Indice Crucial in H1 2023
Higher interest in H1 2023 as a result of cash
being invested in a higher rate guaranteed
Interest income (11,716) (6,004) (5,712) investment vehicle
Smaller loss of Indice Crucial in H1 2023 vs.
Share of associates loss 231
40,972 (40,741) H1 2022
Total $ 383,029
$ 611,519
$ (228,490)

18

EUROPACIFIC METALS INC. Management Discussion and Analysis June 30, 2023

Cash flows for the six months period ended June 30, 2023

During the period ended June 30, 2023, the Company generated $NIL (June 30, 2022 - $150,000) in cash from financing activities. From these cash inflows and the cash reserves available at the beginning of the period, $887,995 (June 30, 2022 - $2,637,587), $55,471 (June 30, 2022 - $250,299) was used towards investing activities and $418,021 (June 30, 2022 - $503,450) was used for working capital, including property exploration and evaluation costs.

LIQUIDITY AND CAPITAL RESOURCES

As of June 30, 2023, the Company had a working capital[1] of $485,642 ($923,174 - December 31, 2022). The Company does not have revenues from operations and relies on outside funding for its continuing financial liquidity. The Company will need additional financing to continue operations and exploration activities.

Management cautions that the Company’s ability to raise additional funding is not certain. Additional funds will be required to pursue the Company’s current business plans. An inability to raise additional funds would adversely impact the future assessment of the Company as a going concern.

SIGNIFICANT ACCOUNTING JUDGMENTS AND USE OF ESTIMATES

The preparation of the financial statements requires management to make estimates and assumptions that affect the reported amounts of assets and liabilities at the date of the financial statements and reported amounts of expenses during the reporting period. Actual outcomes could differ from these estimates. The financial statements include estimates which, by their nature, are uncertain. The impacts of such estimates are pervasive throughout the financial statements and may require accounting adjustments based on future occurrences. Revisions to accounting estimates are recognized in the period in which the estimate is revised, and the revision affects both current and future periods.

The Company’s significant judgments and estimates are disclosed in Note 3 of the audited annual consolidated financial statements for the year ended December 31, 2022.

CHANGES IN ACCOUNTING POLICIES

Accounting policies used in the period, and changes anticipated in future periods, are as set out in the Company’s audited annual consolidated financial statements for the year ended December 31, 2022 (Note 4).

CHANGES IN INTERNAL CONTROLS OVER FINANCIAL REPORTING

There have been no changes in the Company's internal controls over financial reporting during the period ended June 30, 2023, that have materially affected, or are reasonably likely to materially affect, its internal controls over financial reporting.

NON-IFRS MEASURES

1 This is a non-IFRS measurement with no standardized meaning under IFRS and may not be comparable to similar financial measures presented by other issuers. For further information please see the section in this MD&A titled “Non-IFRS Measures”

19

EUROPACIFIC METALS INC. Management Discussion and Analysis June 30, 2023

The Company uses the term "working capital" in this MD&A, which is a non-IFRS measure. The Company calculates working capital as current assets less current liabilities. The Company believes that this measures provide investors with an improved ability to evaluate the performance of the Company.

Non-IFRS measures do not have any standardized meaning prescribed under IFRS. Therefore, such measures may not be comparable to similar measures employed by other companies. The data is intended to provide additional information and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS.

FINANCIAL INSTRUMENTS

The Company’s financial instruments consist of cash, receivables, accounts payable and accrued liabilities. It is management’s opinion that the Company is not exposed to significant interest risk arising from the financial instruments. The Company is exposed to credit risk in relation to accounts receivable, however, most account receivables are in relation to sales tax due from the Canadian government. Credit risk is managed for receivables by seeking prompt payment, monitoring the age of receivables, and making follow up inquiries when receivables are not paid in a timely manner. The Company does not engage in any hedging activities. Financial instruments do not generally expose the Company to risk that is significant enough to warrant reducing via purchasing specific insurance or offsetting financial instruments. Further discussion of these risks is presented in Note 5 of the Company’s audited financial statements for the year December 31, 2022.

RELATED PARTY TRANSACTIONS

Key management compensation

Key management personnel include the Chief Executive Officer, Chief Financial Officer, VP of Exploration, and directors of the Company. The remuneration of key management for the six months periods ended June 30, 2023 and 2022 was as follows:

==> picture [437 x 111] intentionally omitted <==

1Remuneration consists exclusively of salaries, bonuses, health benefits if applicable and consulting fees for key management personnel. Other than the amounts disclosed above, there were no short-term employee benefits granted to key management personnel during the six months.

20

EUROPACIFIC METALS INC. Management Discussion and Analysis June 30, 2023

The following amounts were due to related parties:

==> picture [434 x 79] intentionally omitted <==

RISKS AND UNCERTAINITIES

Risk Factors

Early-stage entities face a variety of risks and, while unable to eliminate all of them, the Company aims to manage and reduce such risks as much as possible. The Company’s ability to mitigate risk, without any cash at its disposal, is, however, extremely limited.

Selecting investments is a competitive process. The Company seeks to maintain an appropriate balance by carefully considering risks to ensure an investment’s level of risk is commensurate with the Company's assessment of the project’s potential.

The Company has a limited history of existence. There can be no assurance that it will be successful in its quest to locate and explore a profitable mineral property. Equity or debt financing will be required to complete the implementation of its business plan. There can be no assurance that the Company will be able to obtain adequate financing to continue. The securities of the Company should be considered a highly speculative investment .

The following risk factors should be given special consideration when evaluating an investment in any of the Company's securities.

Limited Operating History and No History of Earnings

Europacific was incorporated on June 16, 2017 and has a limited operating history and no operating revenues. The Company does not have a history of earnings, nor has it paid any dividends and will not generate earnings or pay dividends in the foreseeable future. The Company has only limited funds with which to continue supporting operations, or alternatively with which to identify and evaluate other potential opportunities and there can be no assurance that the Company will be able to realize either of these goals. In addition, the Company's the business and projects may be financed in all or part by the issuance of additional securities by the Company and this may result in further dilution to the investor, which dilution may be significant and which may also result in a change of control of the Company.

Exploration and Development

Resource exploration and development is a speculative business and involves a high degree of risk. There are no known mineral reserves on the Company's properties. There is no certainty that the expenditures to be made by Europacific

21

EUROPACIFIC METALS INC. Management Discussion and Analysis June 30, 2023

in the exploration of its properties will result in discoveries of commercial quantities of minerals. The marketability of natural resources which may be acquired or discovered by Europacific will be affected by numerous factors beyond the control of Europacific. These factors include market fluctuations, the proximity and capacity of natural resource markets and processing equipment, government regulations, including regulations relating to prices, taxes, royalties, land tenure, land use, importing and exporting of minerals and environmental protection. The exact effect of these factors cannot be accurately predicted, but the combination of these factors may result in a material adverse impact on Europacific's operation and financial condition.

Global Financial Conditions

Global financial conditions have, at various times in the past and may, in the future, experience extreme volatility. Many industries, including the mining industry, are impacted by volatile market conditions. Global financial conditions may be subject to sudden and rapid destabilizations in response to economic shocks or other events, such as developments concerning COVID19, geo-political tensions including acts of war and economic sanctions. A slowdown in the financial markets or other economic conditions, including but not limited to consumer spending, employment rates, business conditions, inflation, fluctuations in fuel and energy costs, consumer debt levels, lack of available credit, the state of the financial markets, interest rates and tax rates, may adversely affect the Company’s growth and financial condition. Future economic shocks may be precipitated by a number of causes, including government debt levels, fluctuations in the price of oil and other commodities, volatility of metal prices, geopolitical instability, changes in laws or governments, war, terrorism, the volatility of currency exchanges inflation or deflation, the devaluation and volatility of global stock markets, pandemics and natural disasters. Any sudden or rapid destabilization of global economic conditions could impact the Company’s ability to obtain equity or debt financing in the future on terms favourable to the Company or at all. In such an event, the Company’s operations and financial condition could be adversely impacted.

Financing Risks

Additional funding will be required to conduct future exploration programs. In addition, if Europacific’s proposed exploration programs are successful, additional funds will be required for the development of an economic mineral body and to place it in commercial production. The only sources of future funds presently available to Europacific are the sale of equity capital, or the offering by Europacific of an interest in its properties to be earned by another party or parties carrying out exploration or development thereof. There is no assurance that any such funds will be available for operations. Failure to obtain additional financing on a timely basis could cause Europacific to reduce or terminate its proposed operations.

Public Health Crises

The Company's business, operations and financial condition could be materially adversely affected by the outbreak of epidemics, pandemics or other health crises, such as COVID-19, and by reactions by government and private actors to such outbreaks. As at the date of this MD&A, the global reactions to the spread of COVID-19 have led to, among other things, significant restrictions on travel, quarantines, temporary business closures and a general reduction in consumer activity. While these effects are expected to be temporary, the duration of the disruptions to business internationally and the related financial impact cannot be estimated with any degree of certainty at this time. Such public health crises can result in disruptions and extreme volatility in financial markets and global supply chains as well as declining trade and market sentiment and reduced mobility of people, all of which could impact commodity prices, interest rates,

22

EUROPACIFIC METALS INC. Management Discussion and Analysis June 30, 2023

credit ratings, credit risk, availability of financing and inflation. The risks to the Company of such public health crises also include risks to employee health and safety and may result in a slowdown or temporary suspension of operations at some or all of the Company's mineral properties. At this point, the extent to which COVID19 may impact the Company remains uncertain; however, it is possible that COVID-19 could have a material adverse effect on the Company's business, results of operations and financial condition. There can be no assurances that the Company will not be required to demobilize its personnel and contractors at any of its mineral projects in due to the ongoing COVID19 pandemic. Any such demobilization may have an adverse impact on the Company’s ability to conduct exploration and further advance its work programs on the affected properties.

OFF BALANCE SHEET ARRANGEMENTS

The Company has not entered into any off-balance sheet arrangements.

QUALIFIED PERSON

Deepak Malhotra, SME-RM, is a Qualified Person as defined by NI 43-101 and has reviewed and approved the scientific and technical information in this MD&A.

OUTSTANDING COMMON SHARE DATA

The following section updates the outstanding common share data provided in the unaudited condensed consolidated interim financial statements for the period ended June 30, 2023:

Shares issued on July 24, 2023 for 30%
interest in EVX Portugal
Shares outstanding at August 28, 2023
Stock Options:
Stock options outstanding at June 30, 2023 and August 28,
2023
Warrants:
Warrants outstanding at June 30, 2023 and August 28,
2023
Common Shares:
Common shares outstanding at June 30, 2023
700,000
51,967,163
52,667,163
4,880,000
540,008

23